Bldg. 9, 31, 33, 35 and 37 - 6/14 thru 7/23 Shutdown Notification
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Jun 13 15:24:00 2000
Message-Id: <82F0D564C5ADD31180EF00508B556451104E97@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'jobrien@mit.edu'" <jobrien@MIT.EDU>,
"'westlund@mit.edu'"
<westlund@MIT.EDU>,
"'randy@mit.edu'" <randy@MIT.EDU>,
"'dineend@mit.edu'" <dineend@MIT.EDU>,
"'engler@mit.edu'"
<engler@MIT.EDU>,
"'mshiffer@mit.edu'" <mshiffer@MIT.EDU>,
"'abernard@mit.edu'" <abernard@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'schedule@mit.edu'" <schedule@MIT.EDU>,
"'archall@mit.edu'" <archall@MIT.EDU>,
"'thane@mit.edu'" <thane@MIT.EDU>, "'loudib@mit.edu'" <loudib@MIT.EDU>,
"'ameswf@mit.edu'" <ameswf@MIT.EDU>,
"'lgallant@mit.edu'" <lgallant@MIT.EDU>,
"'pcollymo@mit.edu'"
<pcollymo@MIT.EDU>,
"'dickp@mit.edu'" <dickp@MIT.EDU>,
"'gerwent@mit.edu'" <gerwent@MIT.EDU>,
"'stiffler@mit.edu'"
<stiffler@MIT.EDU>,
"'emcmill@mit.edu'" <emcmill@MIT.EDU>,
"'pbauer@mit.edu'" <pbauer@MIT.EDU>,
"'benford@space.mit.edu'"
<benford@space.mit.edu>,
"'rjhansen@mit.edu'" <rjhansen@MIT.EDU>,
"'cmo@space.mit.edu'" <cmo@space.mit.edu>,
"'breslau@space.mit.edu'"
<breslau@space.mit.edu>,
"'rcf@space.mit.edu'" <rcf@space.mit.edu>,
"'mmahoney@mit.edu'" <mmahoney@MIT.EDU>, "'krp@mit.edu'" <krp@MIT.EDU>,
"'murphy@space.mit.edu'" <murphy@space.mit.edu>,
"'rdavies@mit.edu'"
<rdavies@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
"'rm-shutdown@mit.edu'" <rm-shutdown@MIT.EDU>, B-Zone <B-Zone@MIT.EDU>,
C-Zone <C-Zone@MIT.EDU>, Vinny Clark <VClark@PLANT.MIT.EDU>,
"'safety@mit.edu'" <safety@MIT.EDU>,
"'cust-coach@mit.edu'"
<cust-coach@MIT.EDU>,
"'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
"'cperry@mit.edu'" <cperry@MIT.EDU>,
"'pbaratta@mit.edu'"
<pbaratta@MIT.EDU>
Date: Tue, 13 Jun 2000 15:21:01 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: 'jobrien@mit.edu'; 'westlund@mit.edu'; 'randy@mit.edu';
> 'dineend@mit.edu'; 'engler@mit.edu'; 'mshiffer@mit.edu';
> 'abernard@mit.edu'; 'shutdowns@mit.edu'; 'schedule@mit.edu';
> 'archall@mit.edu'; 'thane@mit.edu'; 'loudib@mit.edu'; 'ameswf@mit.edu';
> 'lgallant@mit.edu'; 'pcollymo@mit.edu'; dickp@mit.edu; gerwent@mit.edu;
> stiffler@mit.edu; emcmill@mit.edu; pbauer@mit.edu; benford@space.mit.edu;
> rjhansen@mit.edu; cmo@space.mit.edu; breslau@space.mit.edu;
> rcf@space.mit.edu; mmahoney@mit.edu; krp@mit.edu; murphy@space.mit.edu;
> rdavies@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; B-Zone; C-Zone; Vinny
> Clark; safety@mit.edu; cust-coach@mit.edu; dcarlson@mit.edu;
> cperry@mit.edu; pbaratta@mit.edu
> Subject: Bldg. 9, 31, 33, 35 and 37 - 6/14 thru 7/23 Shutdown
> Notification
>
>
Dear Everyone:
During the next 6 weekends, beginning with 6/16 thru 7/23, a special
seamless flooring system (silikal) will be installed on the floors in Bldg.
33. This material (very similar to the system installed in building 35-020
has a strong pungent odor that dissipates rapidly as it cures. In order to
protect the community from this odor, the following procedues will take
place:
* The work will start Friday, Saturday and Sunday evenings at 10:00 pm
and will begin with grinding the floor surface to prepare it for the primer.
The odoriferous material will not be applied until around 12:00 am each
morning.
* Department of Facilities, FCS will shut down the air intake fans in
buildings 9, 31, 37 at 10:00pm and put them back on line at 6:00 am each
morning. The air intake fans in Bldg. 35 will have to be manually shutdown
at 10 PM and then turned on at 6 AM each morning.
* The contractor will seal off the area and install 4 ventilation
units to keep the work under negative pressure and discharge the untreated
exhaust out doors. The will be some odors outdoors in the bldg. 33 area.
Building 33 will be vacant during this work.
* MIT Industrial Hygiene will inspect the first set up.
It is recommended that all windows that have operable sashes be closed. No
Silikal flooring work will take place during normal business hours, only on
those hours listed above.
Vincent Clark
Senior Project Manager
MIT Dept. of Facilities
If there any any concerns, would you please let me know. If you have any
questions about this, please contact Vinny Clark at 3-4749.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 9, 31, 33, 35 and 37
> Date: 6/16/18
> Day: Friday
> Time: 10 PM (6/16) 6 AM (6/17) each night
> System: supply ventilation
> Duration: 6 weekends
> Reason:
> Install flooring (silikal) in Bldg. 33. Has strong odors. It is
> recommended that all windows that have operable sashes be closed.
>
> Effect:
> No access to Bldg. 33 for next 6 weekends. Intake air fans in Bldgs. 9,
> 31, 35 and 37 will be shutdown at 10 PM on Friday night and put back on