[51127] in Hotline Meeting
Bldg. 11 - basement to penthouse - east side - 6/13 - Shutdown Re
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Jun 12 11:47:20 2000
Message-ID: <82F0D564C5ADD31180EF00508B556451104E83@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'cbunker@mit.edu'" <cbunker@mit.edu>,
"'sdimond@mit.edu'"
<sdimond@mit.edu>,
"'chauncy@mit.edu'" <chauncy@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>,
"'schedule@mit.edu'"
<schedule@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
C-Zone
<C-Zone@mit.edu>
Date: Mon, 12 Jun 2000 11:44:58 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: cbunker@mit.edu; sdimond@mit.edu; chauncy@mit.edu;
> shutdowns@mit.edu; schedule@mit.edu
> Cc: shutdown@plant.mit.edu; C-Zone
> Subject: Bldg. 11 - basement to penthouse - east side - 6/13 -
> Shutdown Request
>
>
The following shutdown request for Bldg. 11 - basement to penthouse - Ease
Side on Tuesday, 6/13 is for your information and comment. Would you please
let me know whether this does or does not meet with your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 11 - 004, 032, 143A thru 184A, 228F thru 226A, 311 thru 313
> Date: 6/13/00
> Day: Tuesday
> Time: 7 AM - 3 PM
> System: Chilled Water
> Duration: 8 hours
> Reason:
> To remove Fan Coil Unit #718546 to repair leak and to relocate chilled
> water shutoffs to basement area.
>
> Effect:
> Loss of chilled water (air conditioning) in the above listed areas of the
> building during the shutdown period.
>
>