[49978] in Hotline Meeting
Bldg. 31 - 2/18 - Filter Change/Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Feb 7 08:51:43 2000
Message-Id: <82F0D564C5ADD31180EF00508B55645110490B@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'ameswf@mit.edu'" <ameswf@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'gallant@mit.edu'" <gallant@MIT.EDU>,
"'rcf@space.mit.edu'" <rcf@space.mit.edu>,
"'schedule@mit.edu'"
<schedule@MIT.EDU>,
"'vwong@mit.edu'" <vwong@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Mon, 7 Feb 2000 08:48:42 -0500
Mime-Version: 1.0
Content-Type: text/plain
> To: ameswf@mit.edu; shutdowns@mit.edu; gallant@mit.edu;
> rcf@space.mit.edu; schedule@mit.edu; vwong@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 31 - 2/18 - Filter Change/Shutdown Request
>
>
The following rescheduled filter change/shtudown request for Bldg. 31 on
Friday, 2/18 is for your review and comment. Would you please let me know
if this new date meets with your approval or does not.
Thank you again.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 31
> Date: 2/18/00
> Day: Friday
> Time: 7:30 AM - 11:30AM
> System: Air Handlers 1 and 5
> Duration: 4 hours
> Reason:
> Change filters on Air Handlers 1 and 5 which are on top of the roof.
>
> Effect:
> Loss of supply ventilation, supply cooling and supply heating in Bldg. 31
> during this shutdown period. Each unit will be down for approximately 1
> hour while the other units remain operational.
>
>