Bldg. 54 - Floors 2 thru 18 - 2/6 - Approved Shutdown

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Feb 4 12:46:40 2000

Message-Id: <82F0D564C5ADD31180EF00508B5564511048FC@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: RM-Fire-Prot-Team <rm-fire-prot-team@MIT.EDU>, RM-Utl <rm-utl@MIT.EDU>,
        "'politano@mit.edu'" <politano@MIT.EDU>,
        "'dcarlson@mit.edu'"
	 <dcarlson@MIT.EDU>,
        "'cappucci@mit.edu'" <cappucci@MIT.EDU>,
        "'jfreeman@mit.edu'" <jfreeman@MIT.EDU>,
        "'mmahoney@mit.edu'"
	 <mmahoney@MIT.EDU>, A-Zone <A-Zone@MIT.EDU>,
        Gerry Hughes
	 <ghughes@PLANT.MIT.EDU>,
        "'cust-coach@mit.edu'" <cust-coach@MIT.EDU>,
        Joe Comoletti <jcomolet@PLANT.MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
        "'rm-shutdown@mit.edu'" <rm-shutdown@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>,
        "'schedule@mit.edu'" <schedule@MIT.EDU>
Date: Fri, 4 Feb 2000 12:43:09 -0500 
Mime-Version: 1.0
Content-Type: text/plain

> To: 	RM-Fire-Prot-Team; RM-Utl; politano@mit.edu; dcarlson@mit.edu;
> cappucci@mit.edu; jfreeman@mit.edu; mmahoney@mit.edu; A-Zone; Gerry
> Hughes; cust-coach@mit.edu; Joe Comoletti
> Cc: 	shutdown@plant.mit.edu; rm-shutdown@mit.edu; shutdowns@mit.edu;
> schedule@mit.edu
> Subject: 	Bldg. 54 - Floors 2 thru 18 - 2/6 - Approved Shutdown
> 
> 
The following approved shutdown for Bldg. 54 - Floors 2 thru 18 on Sunday,
2/6 is for your information.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 54 - Floors 2 thru 18
> Date: 2/6/00
> Day: Sunday
> Time: 8 AM - 12 Noon
> System: Perimeter air supply ventilation, Air Handlers 1 and 2, smoke
> detectors
> Duration: 4 hours
> Reason: 
> Prevent smoke and burning odors from entering building ventilation system.
> Smoke and burning work being done in 20th floor penthouse.
> 
> Effect: 
> Loss of supply ventilation and supply heating during shutdown period.
> There will be posted signage throughout building re this shutdown.
> Heating for perimeter will be on but effectiveness reduced. 
> 
> 