[49933] in Hotline Meeting
Bldg. 35 - 105, 118, 122 and upper floors - 2/8 - Shutdown Reques
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Feb 3 11:35:10 2000
Message-Id: <82F0D564C5ADD31180EF00508B5564511048E5@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'stiffler@mit.edu'" <stiffler@MIT.EDU>,
"'emcmill@mit.edu'"
<emcmill@MIT.EDU>,
"'dickp@mit.edu'" <dickp@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
"'schedule@mit.edu'"
<schedule@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Thu, 3 Feb 2000 11:32:08 -0500
Mime-Version: 1.0
Content-Type: text/plain
> To: stiffler@mit.edu; emcmill@mit.edu; dickp@mit.edu; shutdowns@mit.edu;
> schedule@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 35 - 105, 118, 122 and upper floors - 2/8 - Shutdown
> Request #2
>
>
The following shutdown request for Bldg. 35 - 105, 118, 122 and upper floors
on Tuesday, 2/8 is for your review and comment. Would you please let me
know whether this does or does meet with your approval.
Thank you again.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 35-105, 118, 122 and upper floors
> Date: 2/8/00
> Day: Tuesday
> Time: 7:30 AM - 3:30 PM
> System: Hot and cold domestic water
> Duration: 8 hours
> Reason:
> To relocate existing pipes.
>
> Effect:
> Loss of hot and cold domestic water. This means that no toilets,
> bathroom, kitchen faucets or drinking fountains will be operational during
> the 8-hour shutdown period.
>
>