Bldg. Bldg. 37 - 06, 172A, 278, 372, 562A, 562, 564, 664, 676 & 6

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Feb 3 08:58:21 2000

Message-Id: <82F0D564C5ADD31180EF00508B5564511048E0@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'emcmill@mit.edu'" <emcmill@MIT.EDU>,
        "'stiffler@mit.edu'"
	 <stiffler@MIT.EDU>,
        "'dickp@mit.edu'" <dickp@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'schedule@mit.edu'"
	 <schedule@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Thu, 3 Feb 2000 08:55:26 -0500 
Mime-Version: 1.0
Content-Type: text/plain

> To: 	emcmill@mit.edu; stiffler@mit.edu; dickp@mit.edu; shutdowns@mit.edu;
> schedule@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. Bldg. 37 - 06, 172A, 278, 372, 562A, 562, 564, 664,
> 676 & 678- 2/8 - Shutdown Request #2
> 
> 
The following shutdown request for Bldg. 35 - 122, 118, 105 & upper floors
on Tuesday, 2/8 is for your information and comment.  Would you please let
me know whether this does or does not have your approval.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 37 - 06, 172A, 278, 372, 562A, 562, 564, 664, 676 & 678
> Date: 2/8/00
> Day: Tuesday
> Time: 7:30 AM - 3:30 PM
> System: Hot and cold domestic water
> Duration: 8 hours
> Reason: 
> To relocate existing pipes.
> 
> Effect: 
> Loss of hot and cold water in Bldg. 37.  This means that no toilets,
> bathroom kitchen faucets or drinking fountains will be operational during
> the shutdown period.
> 
> 