Bldg. E25 - 2/16 - Shutdown Request #2

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Feb 1 13:58:37 2000

Message-Id: <82F0D564C5ADD31180EF00508B5564511048BC@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'bengel@mit.edu'" <bengel@MIT.EDU>,
        "'sdowney@mit.edu'"
	 <sdowney@MIT.EDU>,
        "'andrea@psyche.mit.edu'" <andrea@psyche.mit.edu>,
        "'jrauch@mit.edu'" <jrauch@MIT.EDU>,
        "'hegarty@mit.edu'"
	 <hegarty@MIT.EDU>,
        "'bnbauer@mit.edu'" <bnbauer@MIT.EDU>,
        "'jmganno@mit.edu'" <jmganno@MIT.EDU>,
        "'shyoung@mit.edu'"
	 <shyoung@MIT.EDU>,
        "'cjbeal@mit.edu'" <cjbeal@MIT.EDU>,
        "'schedule@mit.edu'" <schedule@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>,
        "'elworthi@mit.edu'" <elworthi@MIT.EDU>,
        "'bmalone@mit.edu'" <bmalone@MIT.EDU>, "'cac@mit.edu'" <cac@MIT.EDU>,
        "'roge@med.mit.edu'" <roge@med.mit.edu>,
        "'cpoon@mit.edu'"
	 <cpoon@MIT.EDU>,
        "'edwa@med.mit.edu'" <edwa@med.mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Tue, 1 Feb 2000 13:55:34 -0500 
Mime-Version: 1.0
Content-Type: text/plain

> To: 	bengel@mit.edu; sdowney@mit.edu; andrea@psyche.mit.edu;
> jrauch@mit.edu; hegarty@mit.edu; bnbauer@mit.edu; jmganno@mit.edu;
> shyoung@mit.edu; cjbeal@mit.edu; schedule@mit.edu; shutdowns@mit.edu;
> elworthi@mit.edu; bmalone@mit.edu; cac@mit.edu; roge@med.mit.edu;
> cpoon@mit.edu; edwa@med.mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. E25 - 2/16 - Shutdown Request #2
> 
> 
The following shutdown request #2 for Bldg. E25 on Wednesday, 2/16 is for
your review and comment.  Would you please let me know whether this does or
does not meet with your approval.

Thank you again.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: E25 - entire building
> Date: 2/16/00
> Day: Wednesday
> Time: 7 AM - 11 AM
> System: All heat & cooling operations at pneumatic valves; compressed
> control air and compressed lab air
> Duration: 4 hours
> Reason: 
> Installation of air filters on compressed air for removal of oil in
> system.
> 
> Effect: 
> Loss of supply ventilation, supply cooling, supply heating, compressed
> control and compressed lab air during shutdown period.
> 
> 