[49888] in Hotline Meeting
Bldg. 35 - 118, 122 & Rest of building - 2/8 - Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Jan 31 10:43:33 2000
Message-Id: <82F0D564C5ADD31180EF00508B5564511048A3@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'stiffler@mit.edu'" <stiffler@MIT.EDU>,
"'emcmill@mit.edu'"
<emcmill@MIT.EDU>,
"'dickp@mit.edu'" <dickp@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
"'schedule@mit.edu'"
<schedule@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Mon, 31 Jan 2000 10:40:36 -0500
Mime-Version: 1.0
Content-Type: text/plain
> To: stiffler@mit.edu; emcmill@mit.edu; dickp@mit.edu; shutdowns@mit.edu;
> schedule@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 35 - 118, 122 & Rest of building - 2/8 - Shutdown
> Request
>
>
The following shutdown request for Bldg. 35 - 118, 122 and the rest of the
building is for your information and comment.
Would you please let me know whether this does or does not meet with your
approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 35-118, 122 and rest of building
> Date: 2/8/00
> Day: Tuesday
> Time: 5 AM - 10 AM
> System: Low pressure steam, heating
> Duration: 5 hours
> Reason:
> To replace radiators with new cabinet heaters.
>
> Effect:
> Loss of low pressure steam (heating) in rooms 118, 122 and rest of
> building 35 during the 5-hour shutdown period.
>
>