[49860] in Hotline Meeting
Bldg. 6 - 3rd Floor Labs - 1/31 - Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Jan 27 12:48:47 2000
Message-Id: <82F0D564C5ADD31180EF00508B556451104878@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'naylor@mit.edu'" <naylor@MIT.EDU>,
"'akelsey@mit.edu'"
<akelsey@MIT.EDU>, "'mbj@mit.edu'" <mbj@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Thu, 27 Jan 2000 12:45:50 -0500
Mime-Version: 1.0
Content-Type: text/plain
> To: naylor@mit.edu; akelsey@mit.edu; mbj@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 6 - 3rd Floor Labs - 1/31 - Shutdown Request
>
>
The following shutdown request for Bldg. 6 - 3rd floor labs on Monday, 1/31
is for your review and comment. Would you please let me know whether this
does or does not have your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 6 - 3rd floor labs
> Date: 1/31/00
> Day: Monday
> Time: 7;30 AM - 2:30 PM
> System: Make-Up Air (Return Fan-4)
> Duration: 7 hours
> Reason:
> Investigate existing duct, clean and repair.
>
> Effect: