Bldgs. E18 and E19 - 1/27 - Filter Change/Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Jan 20 11:20:09 2000
Message-Id: <82F0D564C5ADD31180EF00508B556451104837@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'rmelo@mit.edu'" <rmelo@MIT.EDU>, "'aufiero@mit.edu'"
<aufiero@MIT.EDU>,
"'jmganno@mit.edu'" <jmganno@MIT.EDU>,
"'shyoung@mit.edu'" <shyoung@MIT.EDU>,
"'nedivi@mit.edu'"
<nedivi@MIT.EDU>,
"'dshea@mit.edu'" <dshea@MIT.EDU>,
"'safety@mit.edu'"
<safety@MIT.EDU>,
"'joanf@mit.edu'" <joanf@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Thu, 20 Jan 2000 11:17:22 -0500
Mime-Version: 1.0
Content-Type: text/plain
> To: rmelo@mit.edu; aufiero@mit.edu; jmganno@mit.edu; shyoung@mit.edu;
> nedivi@mit.edu; dshea@mit.edu; safety@mit.edu; joanf@mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldgs. E18 and E19 - 1/27 - Filter Change/Shutdown Request
>
>
The following filter change/shutdown request for Bldgs. E18 and E19 on
Thursday, 1/27 is for your review and comment. Would you please let me know
whether this does or does not meet with your approval.
Thank you.
Andrea Nichols
Operations Centr
8-7872
> Status: Normal
> Building: E18 and E19
> Date: 1/27/00
> Day: Thursday
> Time: 7 AM - 3 PM
> System: Supply ventilation, supply cooling and supply heating
> Duration: 8 hours
> Reason:
> Change filter bags on Fan Supply: AH- 7-2 (PM#700698), Air Handler 7-3
> (PM#700699), Air Handler 7-4 (PM#700690), Air Handler 7B2 (PM#700672), Air
> Handler 7B1 (PM#700671) and Air Handler B-3 (PM#700673).
>
> Effect:
> Loss of supply ventilation, supply cooling and supply heating on E18 - 6th
> floor, E18 - 4th Floor Clinic; E18 - 2nd floor, E19 - 2nd and 3rd floors
> and E18 - 3rd Floor. Each unit will be down for 1 1/2 hours while the
> others remain operational.
>
>