Bldgs. 31 & 17 - 1/13 PM - 1/14 AM - Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Jan 6 08:08:35 2000
Message-Id: <82F0D564C5ADD31180EF00508B55645110476D@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'ameswf@mit.edu'" <ameswf@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'gallant@mit.edu'" <gallant@MIT.EDU>,
"'rcf@space.mit.edu'" <rcf@space.mit.edu>,
"'schedule@mit.edu'"
<schedule@MIT.EDU>,
"'vwong@mit.edu'" <vwong@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Thu, 6 Jan 2000 08:06:21 -0500
Mime-Version: 1.0
Content-Type: text/plain
> To: ameswf@mit.edu; shutdowns@mit.edu; gallant@mit.edu;
> rcf@space.mit.edu; schedule@mit.edu; vwong@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldgs. 31 & 17 - 1/13 PM - 1/14 AM - Shutdown Request
>
>
The following shutdown request for Bldgs. 31 and 17 for Thursday PM (1/13)
and Friday AM (1/14) is for your review and comment. Would you please let
me know whether this does or does not meet with your approval.
Thanks very much.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 31 and 17
> Date: 1/13/14
> Day: Thursday
> Time: 9 PM (1/13) - 7 AM (1/14)
> System: 120/208 Volt Normal Power Only
> Duration: 10 hours
> Reason:
> High voltage splice in Manhole 17 for Buildings 33/35 project.
>
> Effect:
> Loss of 120/208 volt normal power. Power: access controls, building
> power, computers, lighting in corridors/stairs. Air: supply ventilation,
> supply cooling, supply heating, exhaust laboratory, exhaust general,
> exhaust toilet, compressed control and compressed lab air; Steam:
> condensate return.
>
>