Bldg. 37 - See Room Listing Below - 12/20 - Emergency Shutdown
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Dec 20 08:15:17 1999
Message-Id: <82F0D564C5ADD31180EF00508B5564511046C4@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'pbauer@mit.edu'" <pbauer@MIT.EDU>,
"'benford@space.mit.edu'"
<benford@space.mit.edu>,
"'cmo@space.mit.edu'" <cmo@space.mit.edu>,
"'breslau@space.mit.edu'" <breslau@space.mit.edu>,
"'rcf@space.mit.edu'"
<rcf@space.mit.edu>,
"'rjhans@mit.edu'" <rjhans@MIT.EDU>, "'kane@mit.edu'" <kane@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'schedule@mit.edu'" <schedule@MIT.EDU>,
"'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
"'jfreeman@mit.edu'"
<jfreeman@MIT.EDU>,
"'mmahoney@mit.edu'" <mmahoney@MIT.EDU>, B-Zone
<B-Zone@MIT.EDU>,
"'gustafson@mit.edu'" <gustafson@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
"'rm-shutdown@mit.edu'" <rm-shutdown@MIT.EDU>
Date: Mon, 20 Dec 1999 08:13:27 -0500
Mime-Version: 1.0
Content-Type: text/plain
> To: pbauer@mit.edu; benford@space.mit.edu; cmo@space.mit.edu;
> breslau@space.mit.edu; rcf@space.mit.edu; rjhans@mit.edu; kane@mit.edu;
> shutdowns@mit.edu; schedule@mit.edu; dcarlson@mit.edu; jfreeman@mit.edu;
> mmahoney@mit.edu; B-Zone; gustafson@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu
> Subject: Bldg. 37 - See Room Listing Below - 12/20 - Emergency
> Shutdown
>
>
The following Emergency shutdown for Bldg. 37 - 184, 292, 292A, 398, 384J,
384, 392, 498, 484J, 484 Svc., 482, 482A, 598, 584J, 582A, 698, 684J, 684,
684A, 684B, 684C, 682, 696 and 680 for today, Monday, December 21 is for
your information.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Emergency
> Building: 37
> Date: 12/20/99
> Day: Monday
> Time: 11 AM - 3 PM
> System: Cold Domestic Water
> Duration: 4 hours
> Reason:
> Replace two broken valves.
>
> Effect:
> Loss of cold domestic water in the above listed rooms. This means that no
> toilets, bathroom kitchen, lab cold water faucets or drinking fountains
> will be operational during the 4-hour shutdown period.
>
>