[49518] in Hotline Meeting
Bldg. 2 - 006 & rest of building- 12/20 - Chilled Water/Supply Co
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Dec 15 14:49:01 1999
Message-Id: <82F0D564C5ADD31180EF00508B556451104692@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'cappozzi@math.mit.edu'" <cappozzi@math.mit.edu>,
"'tivon@math.mit.edu'" <tivon@math.mit.edu>,
"'akelsey@mit.edu'"
<akelsey@MIT.EDU>, "'mbj@mit.edu'" <mbj@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'schedule@mit.edu'" <schedule@MIT.EDU>,
"'wjfitz@mit.edu'" <wjfitz@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Wed, 15 Dec 1999 14:47:15 -0500
Mime-Version: 1.0
Content-Type: text/plain
> To: cappozzi@math.mit.edu; tivon@math.mit.edu; akelsey@mit.edu;
> mbj@mit.edu; shutdowns@mit.edu; schedule@mit.edu; wjfitz@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 2 - 006 & rest of building- 12/20 - Chilled
> Water/Supply Cooling Shutdown Request
>
>
The following chilled water/supply cooling shutdown request for Bldg. 2 -
006 and rest of building on Monday, 12/20 is for your information and
comment. Would you please let me know whether this does or does not meet
with your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 2-006 (and rest of building)
> Date: 12/20/99
> Day: Monday
> Time: 8 AM - 12 Noon
> System: Chilled Water Pumps #710082 & 710083
> Duration: 4 hours
> Reason:
> To rewire two pumps and place pump 3 on Magnetic status & pump 2 on
> Variable Speed Drive.
>
> Effect:
> Loss of chilled water and supply cooling in Bldg. 2. during shutdown
> period.
>
>