[49502] in Hotline Meeting
Bldg. 66 - 12/16 - All Hot & Cold Water Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Dec 14 10:14:47 1999
Message-Id: <82F0D564C5ADD31180EF00508B55645110467D@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'swetzel@mit.edu'" <swetzel@MIT.EDU>,
"'patsys@mit.edu'"
<patsys@MIT.EDU>,
"'schedule@mit.edu'" <schedule@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Tue, 14 Dec 1999 10:12:53 -0500
Mime-Version: 1.0
Content-Type: text/plain
> To: swetzel@mit.edu; patsys@mit.edu; schedule@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 66 - 12/16 - All Hot & Cold Water Shutdown Request
>
>
The following shutdown request for Bldg. 66 on Thursday, 12/16 is for your
information and comment. Would you please let me know whether this does or
does not have your approval.
Thanks very much.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 66
> Date: 12/16/99
> Day: Thursday
> Time: 7 PM - 11 PM
> System: Hot and Cold Water (Domestic & Lab Process)
> Duration: 4 hours
> Reason:
> Tie-in new non-potable (Process) water system.
>
> Effect:
> Loss of hot and cold domestic water (affects toilets, bathroom, kitchen
> and lab sink water faucets) and drinking water as well as hot and cold lab
> process water (affects any water used for lab equipment) during 4
> hour-shutdown period.
>
>