Bldg. 41 - 12/10 - Approved Electrical Power Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Dec 9 11:05:58 1999

Message-Id: <82F0D564C5ADD31180EF00508B556451104658@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: RM-3rdShift <rm-3rdshift@MIT.EDU>, Neal Phalan <phalan@PLANT.MIT.EDU>,
        Joe Kay <jakay@PLANT.MIT.EDU>,
        Steven Gilligan <sgilliga@PLANT.MIT.EDU>, RM-Utl <rm-utl@MIT.EDU>,
        "'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
        "'cappucci@mit.edu'" <cappucci@MIT.EDU>,
        "'jfreeman@mit.edu'"
	 <jfreeman@MIT.EDU>,
        "'mmahoney@mit.edu'" <mmahoney@MIT.EDU>, D-Zone
	 <D-Zone@MIT.EDU>,
        "'pjotoole@plant.mit.edu'" <pjotoole@plant.mit.edu>,
        James Sullivan <jsulliva@PLANT.MIT.EDU>,
        "'mmoreira@plant.mit.edu'"
	 <mmoreira@plant.mit.edu>,
        "'cust-coach@mit.edu'" <cust-coach@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
        "'rm-shutdown@mit.edu'" <rm-shutdown@MIT.EDU>,
        "'gallant@mit.edu'"
	 <gallant@MIT.EDU>,
        "'pmccosco@mit.edu'" <pmccosco@MIT.EDU>,
        "'brisson@mit.edu'" <brisson@MIT.EDU>,
        "'jlsmith@mit.edu'"
	 <jlsmith@MIT.EDU>,
        "'delsemil@mit.edu'" <delsemil@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'schedule@mit.edu'"
	 <schedule@MIT.EDU>,
        "'opsnote@mit.edu'" <opsnote@MIT.EDU>
Date: Thu, 9 Dec 1999 11:04:09 -0500 
Mime-Version: 1.0
Content-Type: text/plain

> To: 	RM-3rdShift; Neal Phalan; Joe Kay; Steven Gilligan; RM-Utl;
> dcarlson@mit.edu; cappucci@mit.edu; jfreeman@mit.edu; mmahoney@mit.edu;
> D-Zone; pjotoole@plant.mit.edu; James Sullivan; mmoreira@plant.mit.edu;
> cust-coach@mit.edu
> Cc: 	shutdown@plant.mit.edu; rm-shutdown@mit.edu; gallant@mit.edu;
> pmccosco@mit.edu; brisson@mit.edu; jlsmith@mit.edu; delsemil@mit.edu;
> shutdowns@mit.edu; schedule@mit.edu; opsnote@mit.edu
> Subject: 	Bldg. 41 - 12/10 - Approved Electrical Power Shutdown
> Request
> 
> 
The following approved electrical power shutdown for Bldg. 41 on Friday,
12/10 is for your information.

Please note that the start time is now 2:30 AM rather than 3.  It has been
requested that the electricity be back on at 6:30 AM - hence the change in
time.

Andrea Nichols
Operations Center
8-782

> Status: Normal
> Building:  41
> Date: 12/10/99
> Day: Friday
> Time: 2:30 AM - 6:30 AM
> System: Normal Electrical Power
> Duration: 4 hours
> Reason: 
> Add temporary power for trailer.
> 
> Effect: 
> Loss of Power:  building power, eleveators, computers, telephones,
> lighting, corridor/stairway lighting;  Water:  chilled water (air
> conditioning);  Air:  Supply ventilation, supply cooling, supply heating,
> exhaust laboratory, exhaust-general, exhaust-toilet, compressed control,
> compressed lab air and lab vacuum air;  Steam:  condensate return.
> 
> 