[49195] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 66 - 11/18 - Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Nov 16 09:57:22 1999

Message-Id: <D8716484935DD311A1C30008C75B07F90AD2B2@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>,
        "'patsys@mit.edu'" <patsys@MIT.EDU>
Cc: RM-3rdShift <rm-3rdshift@MIT.EDU>,
        "'shutdown@plant.mit.edu'"
	 <shutdown@plant.mit.edu>
Date: Tue, 16 Nov 1999 09:56:55 -0500
Mime-Version: 1.0
Content-Type: text/plain

> To: 	schedule@mit.edu; shutdowns@mit.edu; patsys@mit.edu
> Cc: 	RM-3rdShift; shutdown@plant.mit.edu
> Subject: 	Bldg. 66 - 11/18 - Shutdown Request
> 
> 
The following shutdown request for Bldg. 66 on Thursday, 11/18 is for your
review and comment.  Would you please let me know whether this does or does
not meet with your approval.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 66
> Date: 11/18/99
> Day: Thursday
> Time: 6 AM - 7 AM
> System: Low pressure steam, Hot Water, (Air handler 1-All Supply Fans)
> Duration: 1 hour
> Reason: 
> Tie-in new potable (domestic)  water heater. * FCS - Shut off Fans  - -
> 3rd Shift  - secure low PSI Steam).
> 
> Effect: 
> Loss of hot domestic water (hot water for bathroom & kitchen faucets), hot
> lab process water (hot water for lab equipment); Air Handler 1 (supply
> ventilation and supply heating)
> 
> 