Bldg. E52 - 126A&B, 252G, 355, 357A, 359, 454, 455, 456, 536, 537

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Nov 15 11:59:55 1999

Message-Id: <D8716484935DD311A1C30008C75B07F90AD2A5@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'lreinher@mit.edu'" <lreinher@MIT.EDU>,
        "'mscoppa@mit.edu'"
	 <mscoppa@MIT.EDU>,
        "'michaela@mit.edu'" <michaela@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        Carl Hagge
	 <CHagge@PLANT.MIT.EDU>, E-Zone <E-Zone@MIT.EDU>,
        "'tr6@mit.edu'"
	 <tr6@MIT.EDU>, "'doucett@mit.edu'" <doucett@MIT.EDU>,
        "'tdoyle@mit.edu'"
	 <tdoyle@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
        "'rm-shutdown@mit.edu'" <rm-shutdown@MIT.EDU>
Date: Mon, 15 Nov 1999 11:59:36 -0500
Mime-Version: 1.0
Content-Type: text/plain

> To: 	lreinher@mit.edu; mscoppa@mit.edu; michaela@mit.edu;
> shutdowns@mit.edu; Carl Hagge; E-Zone; tr6@mit.edu; doucett@mit.edu;
> tdoyle@mit.edu
> Cc: 	shutdown@plant.mit.edu; rm-shutdown@mit.edu
> Subject: 	Bldg. E52 - 126A&B, 252G, 355, 357A, 359, 454, 455, 456,
> 536, 537, 538 & Faculty Club - 11/15 - 28 Asbestos Removal/Emergency
> Shutdown Notification
> 
> 
The following asbestos removal/emergency shutdown notification for Bldg.
E52- 126A&B, 252G, 355, 357A, 359, 454, 455, 456, 536, 537, 538 & Faculty
Club from Monday, 11/15 thru Sunday, 11/28 is for your information.

If you have any questions pertaining to the asbestos removal, please contact
Tammy Doyle at 3-5166.  

If a problem arises in any of the above listed rooms, please let us know and
we will see what we can do. Please call X3-1500.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: E52 -126A&B, 252G, 355, 357A, 359, 454, 455, 456, 536, 537, 538
> & Faculty Club
> Date: 11/15/28
> Day: Monday
> Time: 11:30 AM (11/15) - 3 PM (11/28)
> System: Steam
> Duration: 13 days
> Reason: 
> Asbestos must be removed from certain pipes that affect steam radiators in
> the above listed rooms.
> 
> Effect: 
> Restoration of heat delayed until November 28 because of required asbestos
> removal on certain pipes that affect steam radiators in certain rooms on
> the south side of E52 (in the general vicinity of the following rooms:
> 126A&B, 252G, 355, 357A, 359, 454, 455, 456, 536, 537, 538 & Faculty Club.
> 
> 