N51 and N52 - All Electrical Power - 11/23 PM - 11/24 AM - Revise

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Nov 9 13:18:46 1999

Message-Id: <D8716484935DD311A1C30008C75B07F90AD27B@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'cbdewart@mit.edu'" <cbdewart@MIT.EDU>,
        "'chambe@mit.edu'"
	 <chambe@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'tash@mit.edu'" <tash@MIT.EDU>, "'archall@mit.edu'" <archall@MIT.EDU>,
        "'menos@mit.edu'" <menos@MIT.EDU>, "'mleen@mit.edu'" <mleen@MIT.EDU>,
        "'piene@mit.edu'" <piene@MIT.EDU>, "'bjames@mit.edu'" <bjames@MIT.EDU>,
        "'rmurray@mit.edu'" <rmurray@MIT.EDU>,
        "'opsnote@mit.edu'"
	 <opsnote@MIT.EDU>,
        "'schedule@mit.edu'" <schedule@MIT.EDU>,
        "'lgross@mit.edu'" <lgross@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Tue, 9 Nov 1999 13:10:29 -0500 
Mime-Version: 1.0
Content-Type: text/plain

> To: 	cbdewart@mit.edu; chambe@mit.edu; shutdowns@mit.edu; tash@mit.edu;
> archall@mit.edu; menos@mit.edu; mleen@mit.edu; piene@mit.edu;
> bjames@mit.edu; rmurray@mit.edu; opsnote@mit.edu; schedule@mit.edu;
> lgross@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	N51 and N52 - All Electrical Power - 11/23 PM - 11/24 AM -
> Revised Shutdown Time Request
> 
> 
Dear Everyone:

I goofed -- there is a class from 7 - 10 PM on 11/23.  Therefore, the
Facilities Department would like to begin this shutdown at 11 PM on Tuesday,
11/23 and finish the work on Wednesday, 11/24 at 7 AM.

Would you please let me know if this new time would be acceptable to you.

Thank you again and again and again.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: N51 and N52 - All Electrical Power - 11/23 PM - 11/24 AM -
> Revised Shutdown Request
> Date: 11/23/24
> Day: Tuesday
> Time: 11 PM (11/23) - 7 AM (11/24)
> System: All Electrical Power
> Duration: 8 hours
> Reason: 
> To hook up cable to buss in switch gear for I Link Panel.
> 
> Effect: 
> Loss of Power:  Access Controls, Bldg. Power, Elevators, Computers,
> Telephones, Lighting and lighitng Corridors/Stairs;  Water:  Hot Domestic
> Water (water for bathroom and kitchen faucets);  Air: Supply Ventilation,
> supply cooling, supply heating, exhaust-laboratory, exhaust-general and
> exhaust-toilet air;  Steam:  low pressure and condensate return.
> 
> 