W16 - Kresge Auditorium - 11/8 Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Nov 3 13:39:15 1999

Message-Id: <D8716484935DD311A1C30008C75B07F90AD237@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'mwf@mit.edu'" <mwf@MIT.EDU>, "'mdimauro@mit.edu'" <mdimauro@MIT.EDU>,
        "'diegom@mit.edu'" <diegom@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Wed, 3 Nov 1999 13:38:39 -0500 
Mime-Version: 1.0
Content-Type: text/plain

> To: 	mwf@mit.edu; mdimauro@mit.edu; diegom@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	W16 - Kresge Auditorium - 11/8 Shutdown Request
> 
> 
The following shutdown request for bldg. W16 (Kresge Auditorium) for Monday,
11/8 is for  your information.  Would you please let me know whether this
does or does not meet with your approval.

Thanks very much.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: W16
> Date: 11/8/99
> Day: Monday
> Time: 7 AM - 4 PM
> System: Chilled Water
> Duration: 9 hours
> Reason: 
> Tie-ins for Chapel pipes in Brine Room.
> 
> Effect: 
> Loss of chilled water (air conditioning) in W16 during the shutdown
> period.
> 
> 