[49043] in Hotline Meeting
W16 - Kresge Auditorium - 11/8 Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Nov 3 13:39:15 1999
Message-Id: <D8716484935DD311A1C30008C75B07F90AD237@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'mwf@mit.edu'" <mwf@MIT.EDU>, "'mdimauro@mit.edu'" <mdimauro@MIT.EDU>,
"'diegom@mit.edu'" <diegom@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Wed, 3 Nov 1999 13:38:39 -0500
Mime-Version: 1.0
Content-Type: text/plain
> To: mwf@mit.edu; mdimauro@mit.edu; diegom@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: W16 - Kresge Auditorium - 11/8 Shutdown Request
>
>
The following shutdown request for bldg. W16 (Kresge Auditorium) for Monday,
11/8 is for your information. Would you please let me know whether this
does or does not meet with your approval.
Thanks very much.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: W16
> Date: 11/8/99
> Day: Monday
> Time: 7 AM - 4 PM
> System: Chilled Water
> Duration: 9 hours
> Reason:
> Tie-ins for Chapel pipes in Brine Room.
>
> Effect:
> Loss of chilled water (air conditioning) in W16 during the shutdown
> period.
>
>