[49041] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 33 Basement - 11/4 - Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Nov 3 12:37:40 1999

Message-Id: <D8716484935DD311A1C30008C75B07F90AD235@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedules@mit.edu'" <schedules@MIT.EDU>,
        "'dickp@mit.edu'"
	 <dickp@MIT.EDU>,
        "'rdavies@mit.edu'" <rdavies@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
        Gerry Desmond
	 <gdesmond@PLANT.MIT.EDU>, B-Zone <B-Zone@MIT.EDU>,
        "'rm-shutdown@mit.edu'" <rm-shutdown@MIT.EDU>
Date: Wed, 3 Nov 1999 12:37:12 -0500 
Mime-Version: 1.0
Content-Type: text/plain

> To: 	schedules@mit.edu; dickp@mit.edu; rdavies@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu; Gerry Desmond; B-Zone; rm-shutdown@mit.edu
> Subject: 	Bldg. 33 Basement - 11/4 - Shutdown Request 
> 
> 
The following shutdown request for Bldg. 33 - Basement on Thursday, 11/4 is
for your information and comment. If you have a concern about this, please
let me know.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 33 - Basement
> Date: 11/4/99
> Day: Thursday
> Time: 6:30 AM - 3 PM
> System: Chilled Water to Building
> Duration: 8 hours
> Reason: 
> Cut and cap existing chilled for new construction.
> 
> Effect: 
> None - the chilled water system is off for the season.
> 
> 

home help back first fref pref prev next nref lref last post