Bldg. 36 - Floors 2 thru 8 North Side - 11/15 - Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Nov 2 10:59:01 1999

Message-Id: <D8716484935DD311A1C30008C75B07F90AD220@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'rroscoe@mit.edu'" <rroscoe@MIT.EDU>,
        "'gfp170@mitrlevm.mit.edu'"
	 <gfp170@mitrlevm.mit.edu>,
        "'schedule@mit.edu'" <schedule@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'ndpope@mit.edu'"
	 <ndpope@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Tue, 2 Nov 1999 10:57:09 -0500 
Mime-Version: 1.0
Content-Type: text/plain

> To: 	rroscoe@mit.edu; gfp170@mitrlevm.mit.edu; schedule@mit.edu;
> shutdowns@mit.edu; ndpope@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 36 - Floors 2 thru 8 North Side - 11/15 - Shutdown
> Request
> 
> 
The following shutdown request for Bldg. 36 - Floors 2 thru 8 north Side on
Monday, 11/15 is for your review and comment.  Would you please let me know
whether this does or does not meet with your approval.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 36 - Floors 2 thru 8 North Side
> Date: 11/15/99
> Day: Monday
> Time: 7:30 AM - 1:30 PM
> System: Supply Ventilation (Supply Fan 7A)
> Duration: 6 hours
> Reason: 
> Replace motor on Supply Fan 7A (PM# 702033).
> 
> Effect: 
> Loss of supply ventilation, supply cooling and supply heating during the
> 6-hour shutdown period.  An example of rooms on the North side would be
> 219 thru 293, 215 thru 277, same general areas for 3rd, 4th, and 5th
> floors, 621 thru 695, 605 thru 699, 709 thru 791, 705 thru 799, 817 thru
> 889, and 805 thru 897.
> 
> 