Bldg. E17 and E18 - 10/31 - Fire Alarm System Testing

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Oct 29 08:59:51 1999

Message-Id: <D8716484935DD311A1C30008C75B07F90AD1FC@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: Clara Romero <CRomero@PLANT.MIT.EDU>,
        Design & Construction
	 <DCS@MIT.EDU>,
        Lisa StCroix <LStCroix@PLANT.MIT.EDU>,
        Operators
	 <Operators@PLANT.MIT.EDU>,
        Richard Sirois <RSirois@PLANT.MIT.EDU>,
        RM-3rdShift <rm-3rdshift@MIT.EDU>, RM-CarpCon <rm-carpcon@MIT.EDU>,
        RM-Lock <rm-lock@MIT.EDU>, RM-StrcPnt <rm-strcpnt@MIT.EDU>,
        Sue Crowley
	 <scrowley@PLANT.MIT.EDU>,
        "'wardd@mit.edu'" <wardd@MIT.EDU>,
        "'shyoung@mit.edu'" <shyoung@MIT.EDU>,
        "'jmganno@mit.edu'"
	 <jmganno@MIT.EDU>,
        "'safety@mit.edu'" <safety@MIT.EDU>,
        "'aufiero@mit.edu'" <aufiero@MIT.EDU>,
        "'rmelo@mit.edu'" <rmelo@MIT.EDU>, "'amba@mit.edu'" <amba@MIT.EDU>,
        "'nedivi@mit.edu'" <nedivi@MIT.EDU>,
        "'jmedeiro@mit.edu'" <jmedeiro@MIT.EDU>
Cc: Cust-Coach <cust-coach@MIT.EDU>, MIS-Team <MIS-Team@PLANT.MIT.EDU>,
        RM-Support <RM-Support@MIT.EDU>,
        "'shutdown@plant.mit.edu'"
	 <shutdown@plant.mit.edu>,
        "'rm-shutdown@mit.edu'" <rm-shutdown@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'rjcayer@mit.edu'"
	 <rjcayer@MIT.EDU>,
        Howard  Harrison <HHarriso@PLANT.MIT.EDU>,
        John Denucce <jdenucce@PLANT.MIT.EDU>,
        David Ferrante
	 <dferrant@PLANT.MIT.EDU>,
        Tom Connolly <tconnoll@PLANT.MIT.EDU>
Date: Fri, 29 Oct 1999 08:52:46 -0400
Mime-Version: 1.0
Content-Type: text/plain

> To: 	Clara Romero; Design & Construction; Lisa StCroix; Operators;
> Richard Sirois; RM-3rdShift; RM-CarpCon; RM-Lock; RM-StrcPnt; Sue Crowley;
> wardd@mit.edu; shyoung@mit.edu; jmganno@mit.edu; safety@mit.edu;
> aufiero@mit.edu; rmelo@mit.edu; amba@mit.edu; nedivi@mit.edu;
> jmedeiro@mit.edu
> Cc: 	Cust-Coach; MIS-Team; RM-Support; shutdown@plant.mit.edu;
> rm-shutdown@mit.edu; shutdowns@mit.edu; rjcayer@mit.edu; Howard  Harrison;
> John Denucce; David Ferrante; Tom Connolly
> Subject: 	Bldg. E17 and E18 - 10/31 - Fire Alarm System Testing
> 
> 
The following Fire Alarm testing for E17 and E18 on Sunday, 10/31 is for
your information.  If you have any questions about this, please contact Mr.
Roger Cayer at 8-0856.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: E17 and E18
> Date: 10/31/99
> Day: Sunday
> Time: 6:30 AM - 2 PM
> System: Fire Alarm - Audible testing
> Duration: 7 1/2 hours
> Reason: 
> Audible Testing of the new Fire Alarm system in E17 and E18.  
> 
> Effect: 
> There will be audible testing of the fire alarm system in E17 and E18.
> The contractor always attempts to keep the audible testing at a minimum -
> the frequency will depend upon software errors or hardware failings.
> 
> 