[46778] in Hotline Meeting
RE: Canceled - Approved - Bldg. 8 - 3/4 - Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Mar 3 08:58:13 1999
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
"'cappucci@mit.edu'"
<cappucci@MIT.EDU>,
"'jfreeman@mit.edu'" <jfreeman@MIT.EDU>,
"'mmahoney@mit.edu'" <mmahoney@MIT.EDU>, C-Zone <C-Zone@MIT.EDU>,
Jack Narcotta <JNarcott@PLANT.MIT.EDU>,
Andrea Nichols
<andrea@PLANT.MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>, RM-Shutdown <rm-shutdown@MIT.EDU>,
"'schedule@mit.edu'" <schedule@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'ccarey@mit.edu'" <ccarey@MIT.EDU>,
"'carolr@mit.edu'" <carolr@MIT.EDU>
Date: Wed, 3 Mar 1999 08:54:14 -0500
Dear Everyone:
This shutdown is a duplicate request for Bldgs. 6 and 8 and is therefore
canceled.
We are sorry for the confusion and thank you for taking the time to
respond.
Andrea Nichols
> > Operations Center
> > 8-7872
> >
> >
CANCELED - duplicate request
> > > Status: Normal
> > > Building: 8
> > > Date: 3/4/99
> > > Day: Thursday
> > > Time: 6 AM - 12 Noon
> > > System: Hot domestic water
> > > Duration: 6 hours
> > > Reason:
> > > To install backflow preventors.
> > >
> > > Effect:
> > > Loss of hot domestic water (water used in bathroom and kitchen
> > > faucets) during shutdown period.
> >
> >
>