Bldg. 26 - All Perimeter Heating - 3/4 - Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Feb 26 14:03:44 1999

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'scheuld@mit.edu'" <scheuld@MIT.EDU>,
        "'adams@mitlns.mit.edu'"
	 <adams@mitlns.mit.edu>,
        "'gfp170@mitrlevm.mit.edu'"
	 <gfp170@mitrlevm.mit.edu>,
        "'rmbessette@mit.edu'" <rmbessette@MIT.EDU>,
        "'mparker@mit.edu'" <mparker@MIT.EDU>,
        "'schippie@mit.edu'"
	 <schippie@MIT.EDU>,
        "'edc@mit.edu'" <edc@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>,
        "'safety@mit.edu'" <safety@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Fri, 26 Feb 1999 13:59:56 -0500

> To: 	scheuld@mit.edu; adams@mitlns.mit.edu; gfp170@mitrlevm.mit.edu;
> rmbessette@mit.edu; mparker@mit.edu; schippie@mit.edu; edc@mit.edu;
> shutdowns@mit.edu; safety@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 26 - All Perimeter Heating - 3/4 - Shutdown
> Request
> 
> 
The following shutdown request for Bldg. 26 - All Perimeter Heating - on
3/4 is for your review nd comment. Would you please let me know whether
this does or does not have your approval.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Critical
> Building: 26
> Date: 3/4/99
> Day: Thursday
> Time: 8 AM - 4 PM
> System: Heating Hot Water
> Duration: 8 hours
> Reason: 
> Restore flow to plugged radiators.
> 
> Effect: 
> Loss of all perimeter heating (radiators) during shutdown. There will
> be supply heating available however (air from above).
> 
> 