[46714] in Hotline Meeting
RE: To be Rescheduled -Bldg. 2 - 2/25 - Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Feb 24 07:18:33 1999
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
"'capozzi@math.mit.edu'"
<capozzi@math.mit.edu>,
"'duggins@math.mit.edu'" <duggins@math.mit.edu>,
"'mbj@mit.edu'" <mbj@MIT.EDU>,
"'daisymae@math.mit.edu'"
<daisymae@math.mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>,
Jack Narcotta
<JNarcott@PLANT.MIT.EDU>,
"Larry St. John" <lstjohn@PLANT.MIT.EDU>,
Warren Scott <WScott@PLANT.MIT.EDU>
Date: Wed, 24 Feb 1999 07:14:46 -0500
Dear Everyone:
This is to inform you that the above shutdown request for Bldg. 2 on
2/25 will not take place. As soon as I have a rescheduled date, I will
pass this along to you.
Thank you for your comments.
Andrea Nichols
> ----------
> From: Andrea Nichols
> Sent: Thursday, February 18, 1999 9:39 AM
> To: 'schedule@mit.edu'; 'capozzi@math.mit.edu';
> 'duggins@math.mit.edu'; 'mbj@mit.edu'; 'daisymae@math.mit.edu';
> 'shutdowns@mit.edu'
> Cc: Shutdown
> Subject: Bldg. 2 - 2/25 - Shutdown Request
> Importance: High
>
Canceled
> > Status: Normal
> > Building: 2
> > Date: 2/TBD/99
> > Day: TBD
> > Time: 10 AM - 6 PM
> > System: Low Pressure Steam
> > Duration: 8 hours
> > Reason:
> > Replace riser valves.
> >
> > Effect:
> > Loss of steam heating in building.
>
>