RE: Rescheduled - Bldg. 68 - All Emergency Power System - Now for

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Jan 15 11:23:10 1999

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'jfucillo@mit.edu'" <jfucillo@MIT.EDU>,
        "'jmganno@mit.edu'"
	 <jmganno@MIT.EDU>,
        "'tomlynch@mit.edu'" <tomlynch@MIT.EDU>,
        "'shyoung@mit.edu'" <shyoung@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>,
        "'opsnote@mit.edu'" <opsnote@MIT.EDU>
Date: Fri, 15 Jan 1999 11:20:26 -0500

Update:
Dear Everyone:
The above shutdown request for Bldg. 68 - all Emergency Power System
originally for 2/17 has been rescheduled to 3/5/99. Please note there
has been a change in the Effect section of this also.

Would you please let me know if this new date does or does not have your
approval.

Thank you again.

Andrea Nichols
> 	Operations Center
> 	8-7872
> 
> 	> Status: Normal
> 	> Building: 68 - Entire Building Including Animal Quarters
> 	> Date: 3/05/98
> 	> Day: Friday
> 	> Time: 12:01 AM - 6:30 AM
> 	> System: Emergency Power (emergency lighting, elevators, animal
> care
> 	> area, HVAC equipment, exhaust fans, outlets in labs.
> 	> Duration: 6 1/2 hours (outages - one at around 12:01 AM and
> the other at around 6:00 AM)
> 	> Reason: 
> 	> To test emergency generator - which will be momentary during
> the
> 	> 6 1/2-hour shutdown.
> 	> 
> 	> Effect: 
> 	> The effect will be a momentary loss of emergency power as the
> 	> automatic transfer switch (ATS) transfers from Normal power to
> 	> Emergency power at the beginning of the test.
> 	> There will be another identical momentary shutdown at the end
> of the
> 	> test as the ATS transfers back to Normal power.
> 	> The effects to the Animal care Facility in the sub-basement
> will be
> 	> more lengthy as HVAC equipment cycles through programs that
> keep it
> 	> off longer.
> 	> There are many labs throughout the building with emergency
> outlets
> > that will have the momentary outages described above. 
> 
       Facilities will provide adequate manpower to monitor alarms and
respond to any problems that may arise.