[46319] in Hotline Meeting
RE: Rescheduled - Bldgs. 2, 6, 6A & 14 Now for Sat., 1/16 Shutdow
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Jan 13 14:34:13 1999
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
"'duggins@math.mit.edu'"
<duggins@math.mit.edu>,
"'capozzi@math.mit.edu'" <capozzi@math.mit.edu>,
"'mbj@mit.edu'" <mbj@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
"'adams@mitlns.mit.edu'" <adams@mitlns.mit.edu>,
"'ccarey@mit.edu'"
<ccarey@MIT.EDU>,
"'naylor@mit.edu'" <naylor@MIT.EDU>, "'elp@mit.edu'"
<elp@MIT.EDU>,
"'farideh@mit.edu'" <farideh@MIT.EDU>,
"'rdavies@mit.edu'" <rdavies@MIT.EDU>,
"'sbritt@mit.edu'"
<sbritt@MIT.EDU>,
"'ericf@mit.edu'" <ericf@MIT.EDU>,
"'kglavash@mit.edu'" <kglavash@MIT.EDU>,
"'nlowe@mit.edu'"
<nlowe@MIT.EDU>,
"'narnia@mit.edu'" <narnia@MIT.EDU>, "'mosh@mit.edu'"
<mosh@MIT.EDU>,
"'susanne@mit.edu'" <susanne@MIT.EDU>,
"'bkdavis@mitvma.mit.edu'" <bkdavis@mitvma.mit.edu>,
"'jhlyons@mit.edu'"
<jhlyons@MIT.EDU>,
Andrea Nichols <andrea@PLANT.MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>
Date: Wed, 13 Jan 1999 14:31:25 -0500
Dear Everyone:
I have been informed that the new suggested rescheduled date for this
shutdown is Saturday, January 16 from 7:30 AM - 3:30 PM. Would you
please let me know if this new date would better fit in with your
schedules.
Thanks and I look forward to hearing from you.
Andrea Nichols
Operations Center
8-7872
> > Status: Normal
> > Building: 2, 6, 6A and 14
> > Date: 1/16/99
> > Day: Saturday
> > Time: 7:30 AM - 3:30 PM
> > System: All water - hot and cold domestic and hot and cold lab
> process
> > Duration: 8 hours
> > Reason:
> > Tie in new backflow preventers and add new valves.
> >
> > Effect:
> > Loss of all water in Bldgs. 2, 6, 6A and 14 with the exception of
> > de-ionized water. This means that no bathrooms, kitchen faucets,
> > drinking fountains or equipment requiring hot and cold lab process
> > water will be operational during the shutdown period.
>
>