RE: Temporarily Canceled - Bldgs. 2, 6, 6A & 14 1/12 Shutdown Req

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Jan 11 11:30:28 1999

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
        "'duggins@math.mit.edu'"
	 <duggins@math.mit.edu>,
        "'capozzi@math.mit.edu'" <capozzi@math.mit.edu>,
        "'mbj@mit.edu'" <mbj@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'adams@mitlns.mit.edu'" <adams@mitlns.mit.edu>,
        "'ccarey@mit.edu'"
	 <ccarey@MIT.EDU>,
        "'naylor@mit.edu'" <naylor@MIT.EDU>, "'elp@mit.edu'"
	 <elp@MIT.EDU>,
        "'farideh@mit.edu'" <farideh@MIT.EDU>,
        "'rdavies@mit.edu'" <rdavies@MIT.EDU>,
        "'sbritt@mit.edu'"
	 <sbritt@MIT.EDU>,
        "'ericf@mit.edu'" <ericf@MIT.EDU>,
        "'kglavash@mit.edu'" <kglavash@MIT.EDU>,
        "'nlowe@mit.edu'"
	 <nlowe@MIT.EDU>,
        "'narnia@mit.edu'" <narnia@MIT.EDU>, "'mosh@mit.edu'"
	 <mosh@MIT.EDU>,
        "'susanne@mit.edu'" <susanne@MIT.EDU>,
        "'bkdavis@mitvma.mit.edu'" <bkdavis@mitvma.mit.edu>,
        "'jhlyons@mit.edu'"
	 <jhlyons@MIT.EDU>,
        Andrea Nichols <andrea@PLANT.MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>, Joe Collins
	 <JCollins@PLANT.MIT.EDU>
Date: Mon, 11 Jan 1999 11:27:51 -0500

Dear Everyone:
The above shutdown originally scheduled for 1/12 has been temporarily
canceled. When I have a new date I will send the information along to
you.

For your information.

Andrea Nichols

> The following shutdown request for Bldgs. 2, 6, 6A and 14 on 1/TBD is
> for
> your information and comment. Would you please let me know whether
> this
> does or does not have your approval.
> 
> Thanks very much.
> 
> Andrea Nichols
> Operations Center
> 8-7872
> 
> > Status: Normal
> > Building: 2, 6, 6A and 14
> > Date: 1/TBD/99
> > Day: TBD
> > Time: 7:30 AM - 3:30 PM
> > System: All water - hot and cold domestic and hot and cold lab
> process
> > Duration: 8 hours
> > Reason: 
> > Tie in new backflow preventers and add new valves.
> > 
> > Effect: 
> > Loss of all water in Bldgs.. 2, 6, 6A and 14 with the exception of
> > e-ionized water. This means that no bathrooms, kitchen faucets,
> > drinking fountains or equipment requiring hot and cold lab process
> > water will be operational during the shutdown period. 
> 