The following shutdown request for Bldgs. 7 and 5 (All Electric Power &
Lighting) on 8/5 is for your information and comment. Would you please
let me know if this meets with your approval or not.

Thanks very much.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: Bldgs. 5 and 7
> Date: 8/5/98
> Day: Wednesday
> Time: 9:00 PM - 9:30 PM
> System: All electric power & lighting
> Duration: 1/2 hour
> Reason: 
> To test high voltage cable
> 
> Effect: 
> Loss of Power: Access Controls, building power, elevators, computers,
> lighting; Water:  chilled water (air conditioning), heating hot water;
> Air:  supply ventilation, supply cooling, supply heating,
> exhaust-laboratory, exhaust-general, exhaust-toilet, compressed
> control, compressed lab air and lab vacuum air;   Steam:  condensate
> return.
> 
> 