[44374] in Hotline Meeting
FW: Approved - Bldgs. W31 and W32 All Electric Power and Lighting
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Aug 3 14:47:51 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
"'cappucci@mit.edu'"
<cappucci@MIT.EDU>,
"'jfreeman@mit.edu'" <jfreeman@MIT.EDU>,
"'opsnote@mit.edu'" <opsnote@MIT.EDU>, D-Zone <D-Zone@MIT.EDU>,
"'wpwohlfa@mit.edu'" <wpwohlfa@MIT.EDU>,
Neil Tomlinson
<NTomlins@PLANT.MIT.EDU>,
James Sullivan <jsulliva@PLANT.MIT.EDU>,
Manuel Moreira <mmoreira@PLANT.MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'schedule@mit.edu'" <schedule@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
RM-Support
<RM-Support@MIT.EDU>,
"'cust-coach@mit.edu'" <cust-coach@MIT.EDU>
Date: Mon, 3 Aug 1998 14:41:54 -0400
The following approved Electric Power and Lighting shutdown for Bldgs.
W31 and W32 on 8/5 PM to 8/6 AM is for your information.
Andrea Nichols
Operations Center
8-7872
> > Status: Normal
> > Building: W31 and W32
> > Date: 8/5/06
> > Day: Wednesday PM to Thursday AM
> > Time: 9PM Wednesday to 3 AM Thursday
> > System: All Electric Power and Lighting
> > Duration: 6 hours
> > Reason:
> > To replace high voltage switch gear in transformer room.
> >
> > Effect:
> > Loss of Power: access controls, building power, elevators,
> computers,
> > lighting; water: chilled water (air conditioning); Air: supply
> > ventilation, supply cooling, exhaust general air, exhaust toilet and
> > compressed control air.
>
>