FW: Approved - Bldgs. 7 and 5 (All Electric Power & Lighting) Shu

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Aug 3 14:40:01 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
        "'cappucci@mit.edu'"
	 <cappucci@MIT.EDU>,
        "'jfreeman@mit.edu'" <jfreeman@MIT.EDU>,
        "'mmahoney@mit.edu'" <mmahoney@MIT.EDU>, C-Zone <C-Zone@MIT.EDU>,
        "'wpwohlfa@mit.edu'" <wpwohlfa@MIT.EDU>,
        Neil Tomlinson
	 <NTomlins@PLANT.MIT.EDU>,
        Manuel Moreira <mmoreira@PLANT.MIT.EDU>,
        James Sullivan <jsulliva@PLANT.MIT.EDU>,
        "'mamullow@mit.edu'"
	 <mamullow@MIT.EDU>
Cc: "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'cust-coach@mit.edu'"
	 <cust-coach@MIT.EDU>,
        "'opsnote@mit.edu'" <opsnote@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'schedule@mit.edu'"
	 <schedule@MIT.EDU>
Date: Mon, 3 Aug 1998 14:34:14 -0400

The following approved All Electric Power 7 Lighting shutdown for Bldgs.
7 and 5 on 8/5 is for your information.

Andrea Nichols
Operations Center
8-7872

> > Status: Normal
> > Building: Bldgs. 5 and 7
> > Date: 8/5/98
> > Day: Wednesday
> > Time: 9:00 PM - 9:30 PM
> > System: All electric power & lighting
> > Duration: 1/2 hour
> > Reason: 
> > To test high voltage cable
> > 
> > Effect: 
> > Loss of Power: Access Controls, building power, elevators,
> computers,
> > lighting; Water:  chilled water (air conditioning), heating hot
> water;
> > Air:  supply ventilation, supply cooling, supply heating,
> > exhaust-laboratory, exhaust-general, exhaust-toilet, compressed
> > control, compressed lab air and lab vacuum air;   Steam:  condensate
> > return.
> > 
> > 
> 