[44370] in Hotline Meeting
FW: Approved - Bldgs. E55 and E53 Electric Power and Lighting Shu
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Aug 3 14:12:13 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
"'capucci@mit.edu'"
<capucci@MIT.EDU>,
"'jfreeman@mit.edu'" <jfreeman@MIT.EDU>, E-Zone
<E-Zone@MIT.EDU>,
"'wpwohlfa@mit.edu'" <wpwohlfa@MIT.EDU>,
Neil Tomlinson <NTomlins@PLANT.MIT.EDU>,
James Sullivan
<jsulliva@PLANT.MIT.EDU>,
Manuel Moreira <mmoreira@PLANT.MIT.EDU>, Joe Kay <jakay@PLANT.MIT.EDU>,
Carl Hagge <CHagge@PLANT.MIT.EDU>, Dan Crovo <DCrovo@PLANT.MIT.EDU>,
"'mmahoney@mit.edu'" <mmahoney@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
"'schedule@mit.edu'" <schedule@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
RM-Support <RM-Support@MIT.EDU>,
"'cust-coach@mit.edu'" <cust-coach@MIT.EDU>
Date: Mon, 3 Aug 1998 14:06:26 -0400
The following approved electric power and lighting shutdown for Bldgs.
E55 and E53 on 8/6 is for your information.
Andrea Nichols
Operations Center
8-7872
> > Status: Normal
> > Building: E55 and E53
> > Date: 8/6/98
> > Day: Thursday
> > Time: 3:00 AM and 5:00 AM
> > System: Electric Power & lighting (Emergency generator will supply
> emergency power)
> > Duration: 1 hour between 3 & 5 AM
> > Reason:
> > To perform high voltage testing of newly installed switchgear.
> >
> > Effect:
> > Loss of Power: access controls; building power, computers,
> telephones,
> > lighting; chilled water (air conditioning); there will be no hot and
> > cold domestic water above the fifth floor in E55 only (no bathrooms,
> > drinking fountains kitchen faucets); there will be 1 elevator in E55
> > available; there will be no supply ventilation, supply cooling,
> supply
> > heating, exhaust general air, exhaust toilet air and compressed
> > control air.
> >
> >
>