Bldg. 38 - 301 (also entire building) Sprinkler Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Aug 3 10:37:43 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'susang@mit.edu'" <susang@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Mon, 3 Aug 1998 10:32:02 -0400

> To: 	susang@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 38 - 301 (also entire building) Sprinkler Shutdown
> Request for 8/7
> 
> 
The following sprinkler shutdown for Bldg. 38 - 301 (also affects entire
building) on 8/7 is for your review and comment. Would you please let me
know if this has your approval or not.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 38 - 301 (also includes entire building)
> Date: 8/7/98
> Day: Friday
> Time: 8:00 AM - 4:00 PM
> System: Fire Protection Water
> Duration: 8 hours
> Reason: 
> to reconfigure sprinkler heads for construction project
> 
> Effect: 
> Loss of fire protection water in 38-301 (and also entire building).
> The Safety office will be advised of this. That office will notify the
> Fire Department.
> 
> 