[44356] in Hotline Meeting
Bldgs. 7 and 5 (All Electric Power & Lighting) Shutdown Request f
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Jul 31 09:04:08 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'pmccosco@mit.edu'" <pmccosco@MIT.EDU>,
"'kbarrett@mit.edu'"
<kbarrett@MIT.EDU>,
"'rdavies@mit.edu'" <rdavies@MIT.EDU>,
"'> cwilkes@mit.edu'" <> cwilkes@mit.edu,
"'chambe@mit.edu'"
<chambe@MIT.EDU>,
"'rhwill@mit.edu'" <rhwill@MIT.EDU>,
"'jobrien@mit.edu'" <jobrien@MIT.EDU>,
"'> engler@mitvma.mit.edu'"
<> engler@mitvma.mit.edu,
"'mamullow@mit.edu'" <mamullow@MIT.EDU>,
"'sburke@mit.edu'" <sburke@MIT.EDU>, "'cod@mit.edu'" <cod@MIT.EDU>,
"'> ndk@mit.edu'" <> ndk@mit.edu,
"'decarli@mit.edu'" <decarli@MIT.EDU>,
"'schedule@mit.edu'" <schedule@MIT.EDU>,
"'mgibson@mit.edu'"
<mgibson@MIT.EDU>,
"'> skendall@mit.edu'" <> skendall@mit.edu,
"'jsmith@mit.edu'" <jsmith@MIT.EDU>, "'mleen@mit.edu'" <mleen@MIT.EDU>,
"'patdixon@mit.edu'" <patdixon@MIT.EDU>,
"'sbritt@mit.edu'"
<sbritt@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Fri, 31 Jul 1998 08:58:29 -0400
> To: pmccosco@mit.edu; kbarrett@mit.edu; rdavies@mit.edu; >
> cwilkes@mit.edu; chambe@mit.edu; rhwill@mit.edu; jobrien@mit.edu; >
> engler@mitvma.mit.edu; mamullow@mit.edu; sburke@mit.edu; cod@mit.edu;
> > ndk@mit.edu; decarli@mit.edu; schedule@mit.edu; mgibson@mit.edu; >
> skendall@mit.edu; jsmith@mit.edu; mleen@mit.edu; patdixon@mit.edu;
> sbritt@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldgs. 7 and 5 (All Electric Power & Lighting) Shutdown
> Request for 8/5
>
>
The following shutdown request for Bldgs. 7 and 5 (All Electric Power &
Lighting) on 8/5 is for your information and comment. Would you please
let me know if this meets with your approval or not.
Thanks very much.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: Bldgs. 5 and 7
> Date: 8/5/98
> Day: Wednesday
> Time: 9:00 PM - 9:30 PM
> System: All electric power & lighting
> Duration: 1/2 hour
> Reason:
> To test high voltage cable
>
> Effect:
> Loss of Power: Access Controls, building power, elevators, computers,
> lighting; Water: chilled water (air conditioning), heating hot water;
> Air: supply ventilation, supply cooling, supply heating,
> exhaust-laboratory, exhaust-general, exhaust-toilet, compressed
> control, compressed lab air and lab vacuum air; Steam: condensate
> return.
>
>