FW: Approved - Bldg. 14N Critical shutdown Request for 7/27

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Jul 27 08:40:31 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: RM-2ndShift <rm-2ndshift@MIT.EDU>,
        "'dcarlson@mit.edu'"
	 <dcarlson@MIT.EDU>,
        "'cappucci@mit.edu'" <cappucci@MIT.EDU>,
        "'jfreeman@mit.edu'" <jfreeman@MIT.EDU>,
        David  Foster
	 <dfoster@PLANT.MIT.EDU>, A-Zone <A-Zone@MIT.EDU>,
        Warren Scott
	 <WScott@PLANT.MIT.EDU>,
        "'mmahoney@mit.edu'" <mmahoney@MIT.EDU>,
        "'cust-coach@mit.edu'" <cust-coach@MIT.EDU>,
        Gerry Hughes
	 <ghughes@PLANT.MIT.EDU>
Cc: "'schedule@mit.edu'" <schedule@MIT.EDU>,
        "'rdavies@mit.edu'"
	 <rdavies@MIT.EDU>,
        "'nlowe@mit.edu'" <nlowe@MIT.EDU>,
        "'narnia@mit.edu'"
	 <narnia@MIT.EDU>,
        "'susanne@mitvma.mit.edu'" <susanne@mitvma.mit.edu>,
        "'bkdavis@mitvma.mit.edu'" <bkdavis@mitvma.mit.edu>,
        "'jhlyons@mit.edu'"
	 <jhlyons@MIT.EDU>,
        "'csnyder@mit.edu'" <csnyder@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Date: Mon, 27 Jul 1998 08:32:48 -0400

The following approved Critical shutdown for Bldg. 14N on 7/27 is for
your information.

Andrea Nichols
Operations Center
8-7872

	----------
> Status: Critical
	> Building: 14N
	> Date: 7/27/98
	> Day: Monday
	> Time: 5:00 PM - 12 midnight
	> System: Supply Ventilation, supply cooling
	> Duration: 7 hours or longer
	> Reason: 
	> bearings are bailing in Supply Fan #2 - PM#701203
	> 
	> Effect: 
	> Loss of  supply ventilation and supply cooling during shutdown
period.
	> 
	> 