RE: Bldg. E51 (Entire Bldg.) Critical Shutdown Request for 7/27

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Jul 22 10:18:27 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'lhill@mit.edu'" <lhill@MIT.EDU>,
        "'schedule@mit.edu'"
	 <schedule@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'mdimauro@mit.edu'" <mdimauro@MIT.EDU>,
        "'dlbrooks@mit.edu'"
	 <dlbrooks@MIT.EDU>,
        "'jstein@mit.edu'" <jstein@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>, Joseph Silva
	 <ajsilva@PLANT.MIT.EDU>
Date: Wed, 22 Jul 1998 10:13:09 -0400

Dear Everyone:

	It has been requested that this shutdown take place in the
evening. Please note the new work time will be from 5:00 PM to 11:00 PM
on 7/27. 
	The following critical shutdown request for Bldg. E51 - 100,
215A thru
	234A, 221, 222 thru 238, 302 thru 310, 307 thru 317, 318 thru
332, 321
	thru 300 (Lobby), and 017 (rooms directly affected - but will
also
	affect the entire building) on 7/27 is for  your information and
	comment. Would you please let me know if this meets with your
approval
	or not.

	Thanks very much.

	Andrea Nichols
	Operations Center
	8-7872

	> Status: Critical
	> Building: E51 - 100, 215A thru 234A, 221, 222 thru 238, 017,
302 thru
	> 310, 307 thru 317, 318 thru 332, 321 thru 300 (Lobby) & entire
bldg.
	> Date: 7/27/98
	> Day: Monday
	> Time: 5:00 PM - 11:00 PM
	> System: Supply Ventilation, Supply Cooling and Supply Heating
	> Duration: 6 hours
	> Reason: 
	> Repair at air dampers and filtering systems.
	> 
	> Effect: 
	> Loss of supply ventilation, supply cooling and supply heating
in
	> above listed rooms and also entire building.
	> 
	> 