RE: Case 115673: Bldg. E53 Emergency Shutdown for 7/17
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Jul 16 15:32:52 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'hotline@MIT.EDU'" <hotline@MIT.EDU>
Date: Thu, 16 Jul 1998 15:27:49 -0400
Lou - good- also I just sent out another email advising of the new start
time of 4 AM rather than 6 AM. People were concerned that the building
would not cool off in time for when people arrived at work tomorrow
morning.
Thanks. andrea
----------
From: hotline@MIT.EDU[SMTP:hotline@MIT.EDU]
Sent: Thursday, July 16, 1998 3:31 PM
To: Andrea Nichols
Subject: Case 115673: Bldg. E53 Emergency Shutdown for 7/17
Case 115673 has been recently updated and currently stands as
follows:
-----------
--- Entry: Thursday, Jul 16, 1998 3:01 PM -- Email Received
--
-----------------------------------
Date: Thu, 16 Jul 1998 14:56:42 -0400
To: "'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
"'cappucci@mit.edu'" <cappucci@MIT.EDU>,
"'jfreeman@mit.edu'"
<jfreeman@MIT.EDU>, "'mmahoney@mit.edu'"
<mmahoney@MIT.EDU>,
Paul Motroni <pmotroni@PLANT.MIT.EDU>, E-Zone
<E-Zone@MIT.EDU>,
"'lhill@mit.edu'" <lhill@MIT.EDU>,
"'rdavies@mit.edu'"
<rdavies@MIT.EDU>, "'janets@mit.edu'" <janets@MIT.EDU>,
"'cust-coach@mit.edu'" <cust-coach@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
"'schedule@mit.edu'"
<schedule@MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
RM-Support <RM-Support@MIT.EDU>
Subject: Bldg. E53 Emergency Shutdown for 7/17
> To: dcarlson@mit.edu; cappucci@mit.edu; jfreeman@mit.edu;
> mmahoney@mit.edu; Paul Motroni; E-Zone; lhill@mit.edu;
> rdavies@mit.edu; janets@mit.edu; cust-coach@mit.edu;
> shutdowns@mit.edu; schedule@mit.edu
> Cc: shutdown@plant.mit.edu; RM-Support
> Subject: Bldg. E53 Emergency Shutdown for 7/17
>
>
The following Emergency shutdownf or Bldg. E53 on 7/17 is for
your
information.
Andrea Nichols
Operations Center
8-7872
> Status: Emergency
> Building: E53
> Date: 7/17/98
> Day: Friday
> Time: 6 AM - 8 AM
> System: Air Handler 1 (Cooling)
> Duration: 2 hours
> Reason:
> Strainer must be cleaned.
>
> Effect:
> Loss of cooling in entire building for 2 hours.
>
>
--- Entry: Thursday, Jul 16, 1998 3:30 PM -- larugsi ---
--- Sent E-Mail (Entire Log) To: ANDREA@PLANT.MIT.EDU
O.K. 1410,
Andrea, we will be able to incorporate this issue
with the one already scheduled for the 16th & 17th.
--Lou