Dear Everyone:
The following revised shutdown request for Bldg. E53 normal Electrical
Power for 7/16 PM and 7/17 AM is for your review. Would you please let
me know if the new time has your approval or not.
Thank you.
Andrea Nichols
----------
> Status: Normal
> Building: E53
> Date: 7/16/17
> Day: Thursday
> Time: 8:00 PM - 6:00 AM (formerly 7 PM - 5 AM)
> System: Normal Electrical Power
> Duration: 10 hours
> Reason:
> Cutover new high voltage primary switch.
>
> Effect:
> Loss of Power: Access controls, building power, computers,
telephones,
> lighting, corridors/stairs (lighting); Water: Chilled water
(air
> conditioning), hot domestic water (water for bathroom and
kitchen
> faucets) and heating hot water (for heat); Air: supply
ventilation,
> supply cooling, supply heating, exhaust general air, exhaust
toilet
> air and compressed control air; Steam: condensate return (air
from
> outside).
>
>