[44119] in Hotline Meeting
RE: Revised -Bldgs. E18 and E19 Emergency Power Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Jul 9 13:57:19 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: Plant-All <Plant-ALL@MIT.EDU>, "'aufiero@mit.edu'" <aufiero@MIT.EDU>,
"'rmelo@mit.edu'" <rmelo@MIT.EDU>,
"'shyoung@mit.edu'" <shyoung@MIT.EDU>,
"'jmganno@mit.edu'" <jmganno@MIT.EDU>,
"'kelly@mit.edu'" <kelly@MIT.EDU>,
"'jmedeiro@mit.edu'" <jmedeiro@MIT.EDU>,
"'rlanger@mit.edu'"
<rlanger@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
"'pritch@mit.edu'" <pritch@MIT.EDU>,
"'farrell@mit.edu'"
<farrell@MIT.EDU>,
"'cbunker@mit.edu'" <cbunker@MIT.EDU>,
"'wbarrett@mit.edu'" <wbarrett@MIT.EDU>,
"'edie@mitvmc.mit.edu'"
<edie@mitvmc.mit.edu>,
"'cashaw@mit.edu'" <cashaw@MIT.EDU>,
"'kshooter@mit.edj'" <kshooter@mit.edj>,
"'lambert@mitvma.mit.edu'"
<lambert@mitvma.mit.edu>,
"'tmeehan@mit.edu'" <tmeehan@MIT.EDU>,
"'opsnote@mit.edu'" <opsnote@MIT.EDU>, "'sico@mit.edu'" <sico@MIT.EDU>,
"'honiker@mit.edu'" <honiker@MIT.EDU>,
"'kelley@mit.edu'"
<kelley@MIT.EDU>,
"'wardd@mit.edu'" <wardd@MIT.EDU>,
"'ramnat@mit.edu'"
<ramnat@MIT.EDU>,
Paul Adams <padams@PLANT.MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>, E-Zone <E-Zone@MIT.EDU>
Date: Thu, 9 Jul 1998 13:52:00 -0400
Dear Everyone:
Please note the corrected services affected by this shutdown. If you
have any question, please contact Neil Tomlinson at 8-9174. Would you
also please let me know if this has your approval or not.
Thank you.
Andrea Nichols
Operations Center
8-7872
----------
> Status: Normal
> Building: E18 and E19
> Date: 7/10/98
> Day: Friday
> Time: 6:30 AM - 7:30 AM
> System: Emergency Power - 480X and 208V
> Duration: 1 hour
> Reason:
> Cutover to replace emergency generator
>
> Effect:
> Loss of Power: emergency power, elevators, lighting,
corridors/stairs; Air: Exhaust laboratory air; (Drainage: sanitary and
storm drain; Other: Fire Alarm System.
>
>