[44104] in Hotline Meeting
RE: Rescheduled Again- W20, W23, W31, W32, 7, 5, W4, W1 and W2 N
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Jul 8 16:02:35 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'mwf@mit.edu'" <mwf@MIT.EDU>, "'pdc@mit.edu'" <pdc@MIT.EDU>,
"'djmartin@mit.edu'" <djmartin@MIT.EDU>,
"'kenstone@mit.edu'"
<kenstone@MIT.EDU>,
"'regillya@mit.edu'" <regillya@MIT.EDU>,
"'mwhelan@mit.edu'" <mwhelan@MIT.EDU>,
"'mdimauro@mit.edu'"
<mdimauro@MIT.EDU>,
"'dsmith@mit.edu'" <dsmith@MIT.EDU>,
"'schedule@mit.edu'" <schedule@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'opsnote@mit.edu'" <opsnote@MIT.EDU>,
"'mgibson@mit.edu'" <mgibson@MIT.EDU>,
"'pmccosco@mit.edu'"
<pmccosco@MIT.EDU>,
"'sburke@mit.edu'" <sburke@MIT.EDU>,
"'skendall@mit.edu'" <skendall@MIT.EDU>,
"'jsmith@mit.edu'"
<jsmith@MIT.EDU>,
"'cahners@mit.edu'" <cahners@MIT.EDU>, "'ndk@mit.edu'"
<ndk@MIT.EDU>,
"'decarli@mit.edu'" <decarli@MIT.EDU>,
"'kbarrett@mit.edu'" <kbarrett@MIT.EDU>,
"'cwilkes@mit.edu'"
<cwilkes@MIT.EDU>,
"'chambe@mit.edu'" <chambe@MIT.EDU>,
"'rhwill@mit.edu'" <rhwill@MIT.EDU>, "'src@mit.edu'" <src@MIT.EDU>,
"'jobrien@mit.edu'" <jobrien@MIT.EDU>,
"'engler@mitvma.mit.edu'"
<engler@mitvma.mit.edu>,
"'cod@mit.edu'" <cod@MIT.EDU>, "'tej@mit.edu'"
<tej@MIT.EDU>,
"'cappucci@mit.edu'" <cappucci@MIT.EDU>,
"'jfreeman@mit.edu'" <jfreeman@MIT.EDU>,
"'mamullow@mit.edu'"
<mamullow@MIT.EDU>,
"'dcarlson@mit.edu'" <dcarlson@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>, Susan Personette <spersone@MIT.EDU>,
Richard Finn <RFinn@PLANT.MIT.EDU>
Date: Wed, 8 Jul 1998 15:57:36 -0400
Dear Everyone:
Due to construction/renovation constraints, it has been requested that
the above shutdown be reverted to the original requested dates of 7/16
and 7/17. Would you please let me know if this meets with your approval
or not. If you have any questions about this, please contact Susan
Personette at 3-7474.
Thank you again for your time and patience.
Andrea Nichols
Operations Center
8-7872
----------
> Status: Normal
> Building: W20, W23, W31, W32, 7, 5, W4, W1 and W2
> Date: 7/16/17
> Day: Thursday PM and Friday AM
> Time: 9 - 10 PM (7/16) and 6 - 7 AM (7/17)
> System: Normal Electrical Power
> Duration: 2 hours (1 hr. each)
> Reason:
> To connect buildings W7 and W16 into the high voltage
loop.
>
> Effect:
> Loss of Power: access controls, building power,
elevators, computers,
> telephones, lighting, corridors/stairs lighting;
>
>