Bldg. E53 Normal Electrical Power shutdown Request for 7/16 PM -

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Jul 8 14:46:29 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'lhill@mit.edu'" <lhill@MIT.EDU>, "'rdavies@mit.edu'"
	 <rdavies@MIT.EDU>,
        "'janets@mit.edu'" <janets@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'schedule@mit.edu'"
	 <schedule@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Wed, 8 Jul 1998 14:41:36 -0400

> To: 	lhill@mit.edu; rdavies@mit.edu; janets@mit.edu;
> shutdowns@mit.edu; schedule@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. E53 Normal Electrical Power shutdown Request for
> 7/16 PM - 7/17 AM
> 
> 
The following Normal Electrical Power shutdown request for Bldg. E53 for
7/16 PM - 7/17 AM is for your information and comment. Would you please
let me know if this meets with your approval or not.

Thanks very much.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: E53
> Date: 7/16/17
> Day: Thursday
> Time: 7:00 PM - 5:00 AM
> System: Normal Electrical Power
> Duration: 10 hours
> Reason: 
> Cutover new high voltage primary switch.
> 
> Effect: 
> Loss of Power: Access controls, building power, computers, telephones,
> lighting, corridors/stairs (lighting);  Water: Chilled water (air
> conditioning), hot domestic water  (water for bathroom and kitchen
> faucets) and heating hot water (for heat);  Air: supply ventilation,
> supply cooling, supply heating, exhaust general air, exhaust toilet
> air and compressed control air;  Steam: condensate return (air from
> outside).
> 
> 