FW: Approved - Bldg. E17 - Emergency Power Shutdown Request for 7

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Jul 7 09:28:18 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
        "'cappucci@mit.edu'"
	 <cappucci@MIT.EDU>,
        "'jfreeman@mit.edu'" <jfreeman@MIT.EDU>, E-Zone
	 <E-Zone@MIT.EDU>,
        Neil Tomlinson <NTomlins@PLANT.MIT.EDU>,
        James Sullivan <jsulliva@PLANT.MIT.EDU>,
        Manuel Moreira
	 <mmoreira@PLANT.MIT.EDU>,
        Howard  Harrison <HHarriso@PLANT.MIT.EDU>
Cc: "'shutdown@mit.edu'" <shutdown@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>,
        RM-Support <RM-Support@MIT.EDU>,
        "'cust-coach@mit.edu'" <cust-coach@MIT.EDU>,
        Warren Scott
	 <WScott@PLANT.MIT.EDU>
Date: Tue, 7 Jul 1998 08:55:21 -0400

The following approved shutdown for Bldg. E17 (Emergency Power) on 7/8
is for your information.

Andrea Nichols
Operations Center
8-7872

----------

> Status: Normal
> Building: E17
> Date: 7/8/98
> Day: Wednesday
> Time: 6:30 AM - 7:00 AM
> System: Emergency Power
> Duration: 30 minutes
> Reason: 
> Cutover to replace Emergency Generator
> 
> Effect: 
> Loss of Emergency Power: Access controls, emergency power; building
> power, elevators, computers, telephones, lighting, corridors/stairs
> lighting;  Air: exhaust laboratory air; drainage: sanitary and storm
> drain; Other: Fire Alarm system 
> 
> 