[44005] in Hotline Meeting
Bldgs. E51, E52, E53, E56 and E60 Shutdown Request for 7/11
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Jun 29 13:20:53 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
"'lhill@mit.edu'"
<lhill@MIT.EDU>, "'dwp@mit.edu'" <dwp@MIT.EDU>,
"'dlbrooks@mit.edu'"
<dlbrooks@MIT.EDU>,
"'jstein@mit.edu'" <jstein@MIT.EDU>, "'gwj@mit.edu'"
<gwj@MIT.EDU>,
"'maureen@mit.edu'" <maureen@MIT.EDU>,
"'jbkalb@mit.edu'"
<jbkalb@MIT.EDU>, "'mwf@mit.edu'" <mwf@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'davies@mit.edu'" <davies@MIT.EDU>,
"'janets@mit.edu'" <janets@MIT.EDU>,
"'mscoppa@mit.edu'"
<mscoppa@MIT.EDU>,
"'michaela@mit.edu'" <michaela@MIT.EDU>,
"'dempsey@mit.edu'" <dempsey@MIT.EDU>, "'nlux@mit.edu'" <nlux@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Mon, 29 Jun 1998 13:16:13 -0400
> To: schedule@mit.edu; lhill@mit.edu; dwp@mit.edu; dlbrooks@mit.edu;
> jstein@mit.edu; gwj@mit.edu; maureen@mit.edu; jbkalb@mit.edu;
> mwf@mit.edu; shutdowns@mit.edu; davies@mit.edu; janets@mit.edu;
> mscoppa@mit.edu; michaela@mit.edu; dempsey@mit.edu; nlux@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldgs. E51, E52, E53, E56 and E60 Shutdown Request for
> 7/11
>
>
The following shutdown request for the above listed buildings on 7/11 is
for your information and comment. Would you please let me know if this
meets with your approval or not.
Thanks very much.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: E51, E52, E53, E56 and E60
> Date: 7/11/98
> Day: Saturday
> Time: 6:00 AM - 2:00 PM or longer
> System: Domestic hot and cold water
> Duration: 8 hours or longer
> Reason:
> change 6" water main in E52.
>
> Effect:
> Loss of domestic hot and cold water. This means that there will be no
> bathrooms (toilets and faucets), kitchens or drinking fountains that
> will be operational. The Faculty Club has approved this shutdown.
>
>