Building 50 - All Electrical Shutdown Request for 5/24

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue May 19 08:30:21 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>,
        "'mwf@mit.edu'" <mwf@MIT.EDU>, "'nmosley@mit.edu'"
	 <nmosley@MIT.EDU>,
        "'eisen@mit.edu'" <eisen@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Tue, 19 May 1998 08:27:05 -0400

> To: 	schedule@mit.edu; shutdowns@mit.edu; mwf@mit.edu;
> nmosley@mit.edu; eisen@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Building 50 - All Electrical Shutdown Request for 5/24
> 
> 
The following electrical (except for the main kitchen) shutdown request
for Bldg. 50 - All on 5/24 is for your information and comment. Would
you please let me know if this meets with your approval or not.

Thanks very much.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 50 - All Except for Main Kitchen)
> Date: 5/24/98
> Day: Sunday
> Time: 11:01 AM - 8:00 AM
> System: Electrical
> Duration: 8 hours
> Reason: 
> To move existing electrical panel in 50-010.
> 
> Effect: 
> Loss of Power: access controls, building power, elevators, computers,
> lighting; Air: supply ventilation, supply cooling, supply heating,
> exhaust general air and exhaust toilet air;
> 
> 