[43349] in Hotline Meeting
E25 Emergency Shutdown (Air Handlers 1 and 5 on 5/16/98
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed May 13 14:29:36 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'bengel@mit.edu'" <bengel@MIT.EDU>,
"'bmalone@mit.edu'"
<bmalone@MIT.EDU>,
"'andrea@wccf.mit.edu'" <andrea@wccf.mit.edu>,
"'sheila@wccf.mit.edu'" <sheila@wccf.mit.edu>,
"'cac@mit.edu'"
<cac@MIT.EDU>, "'pbrown@mit.edu'" <pbrown@MIT.EDU>,
"'jcy@wcbicl.mit.edu'" <jcy@wcbicl.mit.edu>,
"'dcarlson@mit.edu'"
<dcarlson@MIT.EDU>,
"'cappucci@mit.edu'" <cappucci@MIT.EDU>,
"'jfreeman@mit.edu'" <jfreeman@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>, E-Zone <E-Zone@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
"'cust-coach@mit.edu'" <cust-coach@MIT.EDU>,
RM-Support
<RM-Support@MIT.EDU>, Warren Scott <WScott@PLANT.MIT.EDU>
Date: Wed, 13 May 1998 14:26:28 -0400
> To: bengel@mit.edu; bmalone@mit.edu; andrea@wccf.mit.edu;
> sheila@wccf.mit.edu; cac@mit.edu; pbrown@mit.edu; jcy@wcbicl.mit.edu;
> dcarlson@mit.edu; cappucci@mit.edu; jfreeman@mit.edu;
> shutdowns@mit.edu; E-Zone
> Cc: shutdown@plant.mit.edu; cust-coach@mit.edu; RM-Support; Warren
> Scott
> Subject: E25 Emergency Shutdown (Air Handlers 1 and 5 on 5/16/98
>
>
The following emergency shutdown for Bldg. E25 (see room listings under
Effect) on 5/16 is for your information.
Andrea Nichols
Operations Center
8-7872
> Status: Emergency
> Building: E25
> Date: 5/16/98
> Day: Saturday
> Time: 8:00 AM - 6:00 PM
> System: Supply ventilation
> Duration: 10 hours
> Reason:
> Clean duct for Room 630. Dirt affecting research in room.
>
> Effect:
> Loss of supply ventilation in Rooms 202 thru 225; 310, 318, 326; 414,
> 418, 422, 426; 610, 612, 114, 616, 625, 630 (Air Handler 1); Loss of
> supply ventilation in Rooms 231, 233, 235A & B, 237, 241, 245, 249,
> 345, 429, 429A, 433, 437, 441, 445, 449, 529, 533, 537, 541, 547, 549,
> 645, 645 A, B, C, D, E, F, G & H, 649 (Air Handler 5).
>
>