[43325] in Hotline Meeting
Rotch Library - 1st, 2nd & 3rd Floors Shutdown Request for 5/19
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue May 12 13:04:44 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'mdepopolo@mit.edu'" <mdepopolo@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Date: Tue, 12 May 1998 13:01:41 -0400
> To: mdepopolo@mit.edu
> Cc: shutdown@plant.mit.edu; shutdowns@mit.edu
> Subject: Rotch Library - 1st, 2nd & 3rd Floors Shutdown Request
> for 5/19
>
>
The following shutdown request for the Rotch Library, Floors 1, 2 and 3
on 5/19 is for your information and comment. Would you please let me
know if this has your approval or not.
Thanks very much.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 7 - Rotch Library, Floors 1, 2 and 3
> Date: 5/19/98
> Day: Tuesday
> Time: 4:00 AM - 8:00 AM
> System: Electrical Power
> Duration: 4 hours
> Reason:
> To tie in new 480 Volt circuit.
>
> Effect:
> Loss of Power: Bldg. power, computers, telephones and lighting only.
>
>