[43170] in Hotline Meeting
RE: Bldg. 48 - Power & Lighting Shutdown Request for 5/7 and 5/8
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon May 4 11:35:25 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'sfrankel@mit.edu'" <sfrankel@MIT.EDU>,
"'hfhemond@mit.edu'"
<hfhemond@MIT.EDU>,
"'mistetri@deslab.mit.edu'"
<mistetri@deslab.mit.edu>,
"'schedule@mit.edu'" <schedule@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>, "'opsnote@mit.edu'"
<opsnote@MIT.EDU>
Date: Mon, 4 May 1998 11:32:30 -0400
The following all electric power and lighting shutdown request for Bldg.
58 on 5/7 and 5/8 is for your information and comment. Would you please
let me know if this meets with your approval or not.
Another shutdown request was sent to you involving Bldgs. 44, 45 and 48
on 5/1. Please ignore that. This shutdown request supersedes that one.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Regular
> > Building: 48
> > Date: 5/7-8
> > Day: Thursday & Friday
> > Time: 7 - 7:30 PM each evening
> > System: All Electric Power and Lighting
> > Duration: 1/2 hr. each evening
> > Reason:
> > To splice high voltage cables that feed building
> > Effect:
> > Loss of Power: access controls, bldg. power, elevators, computers,
> > telephones, lighting, Air: Supply ventilation,
> > supply cooling, supply heating, exhaust laboratory, exhaust general
> > exhaust toilet, compessed control, compressed lab air and lab vacuum
> air; Water: Chilled water (air conditioning); Steam: condensate
> return.
> - Entire building will be supplied from generator (Building will be
> on normal power at 7:31 AM on
> > Friday, 5/8.
> >
> >
>