Bldgs. 2, 4, 6 and 6A 480 Volt Power Shutdown Request for 5/1

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Apr 22 12:44:23 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
        "'duggins@math.mit.edu'"
	 <duggins@math.mit.edu>,
        "'capoccci@math.mit.edu'"
	 <capoccci@math.mit.edu>,
        "'nolan@math.mit.edu'" <nolan@math.mit.edu>,
        "'juliec@mit.edu'" <juliec@MIT.EDU>, "'mbj@mit.eud'" <mbj@mit.eud>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'graham@mit.edu'"
	 <graham@MIT.EDU>,
        "'acherron@mit.edu'" <acherron@MIT.EDU>,
        "'jcentor@mit.edu'" <jcentor@MIT.EDU>,
        "'cwilkes@mit.edu'"
	 <cwilkes@MIT.EDU>,
        "'rroscoe@mit.edu'" <rroscoe@MIT.EDU>, "'frc@mit.edu'" <frc@MIT.EDU>,
        "'cdernay@mit.edu'" <cdernay@MIT.EDU>, "'ndk@mit.edu'" <ndk@MIT.EDU>,
        "'decarli@mit.edu'" <decarli@MIT.EDU>,
        "'vesau@mit.edu'" <vesau@MIT.EDU>,
        "'vjames@mitvmc.mit.edu'"
	 <vjames@mitvmc.mit.edu>,
        "'rrhonda@mit.edu'" <rrhonda@MIT.EDU>,
        "'lpaul@mit.edu'" <lpaul@MIT.EDU>,
        "'adams@mitlns.mit.edu'"
	 <adams@mitlns.mit.edu>,
        "'naylor@mit.edu'" <naylor@MIT.EDU>, "'elp@mit.edu'" <elp@MIT.EDU>,
        "'farideh@mit.edu'" <farideh@MIT.EDU>,
        "'opsnote@mit.edu'" <opsnote@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Wed, 22 Apr 1998 12:41:38 -0400

> To: 	schedule@mit.edu; duggins@math.mit.edu; capoccci@math.mit.edu;
> nolan@math.mit.edu; juliec@mit.edu; mbj@mit.eud; shutdowns@mit.edu;
> graham@mit.edu; acherron@mit.edu; jcentor@mit.edu; cwilkes@mit.edu;
> rroscoe@mit.edu; frc@mit.edu; cdernay@mit.edu; ndk@mit.edu;
> decarli@mit.edu; vesau@mit.edu; vjames@mitvmc.mit.edu;
> rrhonda@mit.edu; lpaul@mit.edu; adams@mitlns.mit.edu; naylor@mit.edu;
> elp@mit.edu; farideh@mit.edu; opsnote@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldgs. 2, 4, 6 and 6A 480 Volt Power Shutdown Request
> for 5/1
> 
> 
The following shutdown request for Bldgs. 2, 4, 6 and 6A on 5/1 is for
your information. Would you please let me know at your earliest
convenience if this date is acceptable to you or not.

Thanks very much.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 2, 4, 6 and 6A
> Date: 5/1/98
> Day: Friday
> Time: 1:00 AM - 7:00 AM
> System: 480 Volt Power
> Duration: 6 hours
> Reason: 
> To install metering equipment in main 480 Volt electrical substation.
> 
> Effect: 
> Loss of all 480V power in Bldgs. 2 such as Lasers, Mechanical Room -
> 006 equipment such as fans, pumps (chilled water - air conditioning),
> condensate return pumps;
> Bldg. 4 - 120/208Volt power in rooms 070 and 082 affecting lights and
> outlets.
> Bldg. 6 and 6A - All 480Volt power to lasers and lab equipment; lights
> and plugs WILL be on.
> 
> 