[42924] in Hotline Meeting

home help back first fref pref prev next nref lref last post

FW:Approved - Bldg. 44 and 45 All Electric Power and Lighting Shu

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Apr 21 14:00:33 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
        "'cappucci@mit.edu'"
	 <cappucci@MIT.EDU>,
        "'mmahoney@mit.edu'" <mmahoney@MIT.EDU>, D-Zone
	 <D-Zone@MIT.EDU>,
        Neil Tomlinson <NTomlins@PLANT.MIT.EDU>,
        William Wohlfarth <wpwohlfa@PLANT.MIT.EDU>,
        Manuel Moreira
	 <mmoreira@PLANT.MIT.EDU>,
        James Sullivan <jsulliva@PLANT.MIT.EDU>,
        "'jfreeman@mit.edu'" <jfreeman@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'cust-coach@mit.edu'"
	 <cust-coach@MIT.EDU>,
        RM-Support <RM-Support@MIT.EDU>
Date: Tue, 21 Apr 1998 13:58:01 -0400

The following approved shutdown for Bldgs. 44 and 45 on 4/23 PM - 4/24
AM is for your information.

Andrea Nichols
Operations Center
8-7872

> > Status: Normal
> > Building: 44 and 45
> > Date: 4/23/24
> > Day: Tuesday
> > Time: 8:30 PM - 7:00 AM
> > System: All Electric Power and Lighting
> > Duration: 10 1/2 hours
> > Reason: 
> > To splice high voltage feeder cables
> > 
> > Effect: 
> > Loss of Power: access controls, bldg. power, elevators, computers,
> > telephones, lighting, corridors/stirs lighting; Air: supply
> > ventilation, supply cooling, supply heating, exhaust-laboratory air,
> > exhaust-general air, exhaust-toilet air, compressed  control air,
> > compressed lab air and lab vacuum air; Steam: condensate return.
> > 
> > 
> 