FCS3 Shutdown Request for 4/14
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Apr 10 15:46:42 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'jmganno@mit.edu'" <jmganno@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'loudib@MIT.EDU'" <loudib@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Fri, 10 Apr 1998 15:44:43 -0400
> To: jmganno@mit.edu; shutdowns@mit.edu; loudib@MIT.EDU
> Cc: shutdown@plant.mit.edu
> Subject: FCS3 Shutdown Request for 4/14
>
>
The following shutdown request for the FCS-3 campus monitor alarm system
is for 4/14. Would you please let me know if this is all right or not.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: Campus-Wide
> Date: 4/14/98
> Day: Tuesday
> Time: 10:00 AM - 12 Noon
> System: FCS3 Alarm Monitoring System
> Duration: 2 hours
> Reason:
> Back-up of data.
>
> Effect:
> The FCS3 campus alarm monitoring system will be down for 2 hours. You
> will be responsible for your own areas.
>
>